
SEDIMENT ROUTING 13.3
costly modifications to the dam will be required to provide large-capacity low-level
outlets.
A major disadvantage of sediment routing is that a significant amount of water must be
released during floods to transport sediments. Sediment routing is most applicable at
hydrologically small reservoirs where the water discharged by large sediment-transporting
floods exceeds reservoir capacity, making water available for sediment release without
infringing on beneficial uses. Some routing operations require the use of real-time
hydrologic forecasting. Sediment routing may not be able to remove previously deposited
sediment or pass the coarsest part of the inflowing load beyond the dam. Thus, routing
needs to begin as early as possible after dam construction to preserve capacity, and
supplemental measures (e.g., flushing, dredging) may also be required.
13.2 SEDIMENT PASS-THROUGH BY SEASONAL
DRAWDOWN
13.2.1 Technique
A reservoir operated under seasonal drawdown is either partially or completely emptied
during the flood season. Seasonal drawdown is conducted during a predetermined period
each year, as opposed to flood routing, which requires that the reservoir level be drawn
down to pass individual flood events whenever they occur.
13.2.2 Partial Drawdown
Under partial drawdown, the reservoir is maintained at a lower pool elevation during the
flood season to increase flow velocity and decrease detention time and sediment trapping.
The pool may temporarily be drawn down even further to route specific events through the
impoundment. Sediment release efficiency is determined by the sediment transport
capacity along the full length of the impoundment, including any backwater area in front
of the dam which will accumulate sediment until an equilibrium profile is established.
Under appropriate conditions, a sediment balance can be achieved with year-round
uninterrupted reservoir operation by using partial drawdown.
13.2.3 Partial Drawdown at Three Gorges Project
An example of partial drawdown is the Three Gorges Project (TGP) on the Yangtze River
in China. General project information is described by Changjiang Water Resources
Commission (1994) and Lu (1995), and sedimentation issues have been described by Lin
et al. (1989, 1993) and Chen (1994).
Construction of the controversial Three Gorges Project began in 1993 and is projected
to require 17 years. When completed it will be the world's largest hydropower project with
18,200 MW of installed capacity in 26 generating units of 700 MW powered by Francis-
type turbines rated at 940 m
3
/s with minimum and maximum operating heads of 71 and
113 m, respectively. Many aspects of the project are both massive and extremely
challenging. The concrete gravity dam, powerhouse, and locks will require over 100 Mm
3
of rock and earth excavation, 30 Mm
3
of embankment construction, and 27 Mm
3
of
concrete. At 175 m, the dam is not unusually tall, but it must be constructed across a river
60 m deep with a mean discharge of 14,300 m
3
/s. The 1084 km
2
reservoir area will