SEDIMENT ROUTING 13.8
Rule curve. In reservoirs which are hydrologically very small, gate operation may be
controlled using a rule curve and discharge measurements at the dam or an upstream
gage station.
Hydrograph prediction. In reservoirs having significant storage or limited discharge
capacity, the pool may be drawn down or emptied in anticipation of flood arrival,
releasing water from the rising limb of the hydrograph and refilling the reservoir with
water from the hydrograph recession. This approach requires real-time prediction of
the inflowing hydrograph to guide gate operation.
These two methods of hydraulic control are discussed in subsequent sections.
13.3.2 Sediment Balance by Flood Routing
Full long-term sediment equilibrium is attained when sediment inflow and discharge are
balanced with respect to both sediment quantity and grain size distribution. This is rarely
achieved: the coarsest fraction of the load will typically continue to accumulate. However,
under favorable conditions pass-through can achieve a sediment balance for all but the
largest inflowing grain sizes, while sustaining a desirable profile extending upstream from
the dam. Even when a sediment balance cannot be achieved, sediment pass-through can
reduce the frequency, cost, and environmental impacts associated with complementary
techniques such as dredging or flushing, or can extend the life of a reservoir where
sediment removal is not considered practical. One example of this technique is provided in
the Feather River case study (Chap. 22). An example on the Isar River in Germany is
described in Sec. 18.3.4.
Sediment release efficiency, the ratio of sediment release to sediment inflow, can vary
widely in drawdown routing. It will exceed 100 percent when there is net scour from the
reservoir of previously deposited material. If storage capacity is to be stabilized, sediment
deposited within the reservoir by smaller events outside of the routing period must be
mobilized and transported beyond the dam during pass-through events, and the sediment
release efficiency during the routing period must exceed 100 percent. The adverse
environmental impact of this increase in solids may be small or negligible because
increased sediment loads will occur during periods of naturally high sediment
concentration and transport capacity, and dilution by flood discharge will limit the
increase in solids concentration. This is different from flushing, which tends to release
sediment during periods of relatively low flow and produces high sediment concentrations.
To achieve a sediment balance for a particular grain size, pass-through periods must
produce bed shear values adequate to transport the target material through the entire length
of the impoundment and beyond the dam. The duration of the discharge must also be
adequate to release the total inflowing load in the target grain size that is delivered to the
reservoir between routing events. Generally, for a given discharge and flow duration, the
entire inflowing sediment load smaller than a certain diameter can be discharged through
the impounded reach at the same rate it is delivered. Somewhat larger grains will be
transported but at a rate slower than the delivery rate. A yet larger size will not be
transported at all once it enters the pool, because of backwater above the outlet at peak
discharges. These two larger sizes will continue to accumulate in the reservoir despite
successful pass-through of finer material (Fig. 13.5). Larger diameter sediments can be
transported by increasing either discharge or flow velocity (i.e., more drawdown), and the
amount of transportable material that is released can be increased by prolonging the
duration of routing flows.