control
and
prompt distribution
of
information
to all
members
of the
project team
are
basic requirements
for
a
successful
project. Recognize that,
in
future
weeks
or
years, others will need
to
refer
to the
project
record
for
information. Under
the
best
of
circum-
stances,
the
need will occur because
the
project
has
been eminently
successful
and
others
may
wish
to
dis-
cover
the
secrets
of
success.
Under
the
worst
of
cir-
cumstances,
the
records will
be
needed because
contractor
or
client claims
or
litigation have made
it
necessary
to
determine
how the
project went awry.
Either way,
if the
task
was
performed properly, there
should
be no
fear
of
exposure.
Calculations should always
be
accompanied
by
an
explanation
of
their significance, because other-
wise, their meaning will make interpretation
in
future
years almost impossible. Indeed,
a
good
set of
calculations
usually involves more text than num-
bers.
Engineers come
and go, and the one who
starts
a job may not be the one to finish
—
another
reason
to
make calculations perfectly understandable
by any
likely reader.
Another important element
is the
quality assurance
procedures. Protocols should
be
established
for
• The
calculation
format
•
Checking
the
calculations
•
Reviewing specifications
and
drawings
•
Cross-checking between
disciplines
•
Peer review
•
Final coordination reviews
•
Final signing
and
sealing
of
contract documents.
A
properly conceived
and
implemented quality
assurance plan
is the
cornerstone
of a
successful
project.
If
quality assurance
is not
considered
and
documented
as an
important
facet,
the
result
may be,
at
best,
an
inordinate number
of
costly change
orders
or, at
worst,
a
disastrous
failure.
Project
events usually
fall
into three
stages
during
the
design process:
(1)
preliminary engineering,
(2)
detailed layout,
and (3)
detailed design.
The
general
sequence
of
activities
at
each stage
of
design develop-
ment
is
described
in the
following
sections.
1
7-2.
Preliminary Engineering
The
purpose
of
preliminary engineering
is to
gather
the
information necessary
to
perform
the
design.
If the
preliminary engineering
has
been
properly executed,
all of the
information required
to
complete
the
detailed
design
will
be
within
arm's reach. Additional information
and
details
on
preliminary
engineering
are
contained
in
Sections
25-1
to
25-4.
Need
for
Pumping
Stations
Even
small pumping stations represent
a
substantial
investment
over
the
life
of the
facility
—
particularly
true
with wastewater pumping stations where struc-
ture
size, excavation depths,
and
environmental con-
siderations generally result
in
comparatively greater
costs than those
of
water pumping stations
of an
equivalent
capacity. Therefore, deeper sewers, tunnel-
ing
or
jacking through hills, alternate pipeline routes,
and
other strategies should
be
considered
on a
present
worth
basis with generous allowances
for the
cost
of
operation
and
maintenance
of the
pumping station
before
deciding whether
to
pump.
5ft
e
Selection
Frequently,
an
engineer
has
little choice
in
site selec-
tion
for
wastewater pumping stations because
of
sewer system hydraulics, political considerations,
and
available land. Some aspects
of
site selection could
have
profound implications with respect
to the
cost
of
the
project. These include subsurface conditions, aes-
thetic considerations,
and the
route
of the
force main.
The
concerns
and
considerations associated with
evaluating
and
selecting pumping station sites
are
dis-
cussed
in
Chapter
25 and are
briefly
summarized
in
the
following subsections.
Subsurface
Conditions
The
characteristics
of the
underlying soils
at a
site
often
require some
specific
method
of
construction.
For
example,
a
caisson
may be
required because
of
soft
soils
and
high
ground
water;
thus,
the
configura-
tion
of the
pumping station
is
virtually dictated
by the
caisson and,
in
turn,
by the
subsurface conditions.
This
situation
is
illustrated
in the
Duwamish
Pumping
Station (Example 17-1), where
a
caisson
was
used.
A
caisson must
be
open
at the
bottom
and top for
exca-
vating
the
material inside,
so a
cylinder (designed
as a
ring girder
to
resist wall loads)
is
more
efficient
than
a
box-type structure
in
which
the
necessary internal dia-
phragms
or
struts
are
obstructions. Once
the
structure
has
been sunk
to the
planned elevation,
a
tremie
seal
can be
cast
at the
bottom.
After
curing,
the
structure
can
be
dewatered
and
internal walls
and
slabs
can be
constructed. While this example
is
perhaps somewhat
unusual
in the
United States, wastewater pumping sta-
tions are,
by
their nature,
often
deep structures.
The
location
and
thickness
of floors and
walls
and the
con-
figuration
of
the
structure
are
often
determined
by the
external wall loads
and
buoyancy caused
by
both
hydrostatic
and
passive soil pressures. Therefore,
after