Before
energizing anything,
the
following should
be
done:
71. The
grounding system should
be
tested.
The
best
way to
accomplish this test
is
specified
in
IEEE
81.
The 5-
ohm
value suggested meets code
but is not
very good
for
wet-process equipment. Generally, values
of
less
than
1 ohm can be
obtained without
difficulty.
The
actual value required depends
on the
capacity
and
volt-
age
levels
of the
power system
and
should
be
determined
by the
electrical design engineer.
In
situations
where
a low
enough ground resistance cannot
be
obtained, such
as in
desert areas,
the
design engineer
should have known about
it and
designed
a
ground
mat for the
facility
that would,
at
least, hold potential
gradients
within
values
safe
to
human beings. Check switchgear, yard transformer, pump
and
motor control
centers, motor feeder cables, pumps
and
equipment
at all
electrically connected panels,
and
switchgear
ground
bus for
grounding.
72.
Electrical insulation should
be
tested.
For
low-voltage
(<600
V),
this
is
easily accomplished with meg-ohm
meters that typically apply 1000
V to the
circuitry under test.
For
systems rated over
600 V,
"high-potting"
is
required. Only personnel trained
in
these procedures should attempt high-voltage insulation testing.
73.
Protective devices, such
as
fuses
and
circuit breakers, should
be
checked
at
least visually
for
conformance
to
design documents. Circuit breakers should
be
operated manually
to
ensure that
the
mechanisms
are not
binding. Adjustable circuit breakers
and
protective relays should
be
checked
for
correct settings. Checking
low-voltage motor overload heaters
and
motor starter
fuses
is
specifically omitted
at
this point. Overload
heater
and
motor starter
fuses
should
be
removed
from
all
starters before energizing
the
system. High-volt-
age
starters
and
circuit breakers should
be
racked
out to the
test positions.
In
power systems rated more than 1200
A at 480 V and all
power systems operating
at
over
600 V, it is
strongly recommended that
all
protective
devices
be
tested
by
passing current through
their
sensing ele-
ments
with
a
high-current low-voltage testing
machine—a
task that should normally
be
done
by
contractors
specializing
in
electrical testing.
74.
Electrical gear must
be
vacuumed
out
thoroughly
to
remove construction dust
and
debris.
75.
Every circuit
and
breaker
and
disconnect switch should
be
opened before
the
utility turns
on the
power.
Some
of the
detailed checks
to be
made before
the
utility turns
on the
power
are as
follows:
76.
Cable
and
circuit
are
identified
per
contract specification requirements.
77.
Switchgear
key
interlock scheme prevents paralleling feeders
(if
there
is
more than
one
feeder).
78.
Switchgear door interlock
functions
are
a.
Door cannot
be
opened with switchgear closed.
b.
Switch cannot
be
closed
with door open.
c.
Access
to all
power
fuses
is
possible
only when switches
are
open.
79. All
switchgear secondary
and
low-voltage compartments
are
isolated
by
barriers
from
high-voltage com-
partments.
80.
Switchgear current-limiting
fuses
are
rated
in
accordance with
the
contract documents.
81.
Switchgear safety-glass window makes disconnect blade visible. Stored-energy disconnect switch mecha-
nism
operates.
82.
Switchgear
weatherproofing
(if
outdoor type), ventilation, thermostat,
and
heaters
are
operational.
83.
Switchgear protective relay settings
are in
accordance with manufacturers' recommendations
and
coordina-
tion/short-circuit protection limits. Each incoming line
has
time-delay
overcurrent
and one
time-delay
ground
fault
protective relay.
84.
Pomeads
or
other
cones
on all
power
cables
are
installed properly.
85.
Nameplates, warning,
and
"danger—high
voltage"
signs
are
installed.
86.
Perform high potential (voltage) tests
at
switchgear
for 1 min on
primary
and
secondary circuits. Factory
test reports
on
high potential tests
are
acceptable.
87.
Switchgear schematic control diagrams
are
correct.
88. See
that transformer nameplate data, high-voltage warning signs,
and
high-
and
low-voltage compartment
isolation
are in
place.
89.
Transformer door interlocks: assure
a.
Low-voltage compartment door
can be
opened
first.
b.
High-voltage compartment door cannot
be
opened
first.
90.
Transformer high-voltage compartment switch
fuse
is
operational.