
GEBIDEM DAM AND RESERVOIR 21.6
flow flushing through the outlet begins, typically at discharges between 10 and 20 m
3
/s.
In some years the gates are closed for periods of about 20 minutes, then fully reopened;
the resulting rising and lowering water level facilitates flushing of deposits in the vicinity
of the dam. Some characteristics of flushing events are summarized in Table 21.2. The
column labeled "Gate operations" in the table refers to the number of times the bottom
gates were closed and reopened during the flushing event to facilitate sediment removal.
The amount of solids flushed from the reservoir are not monitored every year, but are
computed by assuming 6 percent solids concentration in the flushing discharge, a value
established by field sampling during early flushing events. Thus, the values for sediment
removed are, in many years, only rough estimates.
More detailed measurements were made during the 1991 flushing event to construct a
sediment budget. The original data for sediment concentration are reported in units of
milliliters per liter of settleable solids as measured in an Imhoff cone, and have been
adjusted to grams per liter by using the conversion factor of 1 mL/L = 1.32 g/L, measured
in the Rhone at Lonoza during the 1995 flushing. Discharge and concentration data at the
dam (Fig. 21.6) reflect the high initial sediment concentration characteristic of flushing
operations. Because of settling of sediments within the gorge, the maximum suspended
solids concentration measured at the channel in the flat downstream reach was 304 g/L,
only 51 percent of the maximum value registered at the dam. The highest suspended
solids concentration measured in the Rhone at the Brigerbad Bridge was 47 g/L,
compared to 2 g/L in the Rhone above the confluence with the Massa. Two-thirds of the
total sediment discharge occurred during the first 5 hours of this 95.5-hour event (Fig.
21.7). Different portions of the reservoir are eroded during the early and later parts of the
flushing, as illustrated in Fig. 21.8, which is based on photogrammetric surveys of the
reservoir during the flushing. A sediment balance based on monitoring at various points
is shown in Table 21.3, showing that much of the material flushed from the reservoir is
deposited in the gorge below the dam, and is not washed downstream until later in the
summer. A sand and gravel operator removes an unquantified volume of sediment from
the system for commercial use. The delta region of the reservoir may he experiencing the
gradual accumulation of material too large to be transported through the impounded reach
TABLE 21.2 Summary of Flushings at Gebidem Dam
Year
Water used,
10
6
m
3
Duration,
hours
Mean purge
flow, m
3
/s
Gate
operations
Solids removed,
10
6
m
3
Solids
concentration, %
1982 2.38 56 11.8 0 0.143 6.0
1983 3.38 48 19.6 2 0.175 5.2
1984 2.97 68 12.1 6 0.178 6.0
1985 2.50 49 14.2 0 0.150 6.0
1986 3.53 45 21.8 0 0.212 6.0
1987 3.20 45 19.8 13 0.192 6.0
1988 2.93 79 10.3 13 0.176 6.0
1989 2.49 49 14.1 1 0.150 6.0
1990 3.18 40 22.1 12 0.191 6.0
1991 2.35 96 6.8 0 0.270 11.5
1992 3.28 151 6.0 61 0.197 6.0
1993 2.48 101 6.8 ? 0.260 10.5