SEDIMENT EXCAVATION 16.22
The dredging project was divided into two phases, one for each arm of the reservoir.
Dredging began in 1987, after being delayed by low water which left inadequate depth
under the prescribed cut to float the dredge. Dredging was undertaken 5 days per week,
24 hours per day, from April into December, with a conventional cutterhead-type dredge
and a flexible high-density polyethylene pipeline. Dredging was not feasible in the
middle of winter because the upper arms of the lake ice over. The dredge, booster pump,
pipeline, and other equipment used on this job were transported to the site in 17 tractor-
trailers. A staging area with good road access was provided at the edge of the lake for the
contractor to use for equipment setup and launching, and for storage of equipment and
supplies for the job.
The first dredging phase did not need a booster pump because it was close to the
containment area. The second phase used a single barge-mounted diesel booster pump at
the edge of the lake to pump dredged material into the containment area. Hospital-class
mufflers were specified for the booster, since the lake is lined with residences. Despite
the numerous residences and 24-hour operation, there were no noise complaints during
either phase of the work. Dredging reportedly generated a very small turbidity plume
which caused no problems. Deposited sediments in the lake averaged 66 percent clay, 33
percent silt, and 1 percent sand (Fitzpatrick et al., 1985). Because dredging was
concentrated in the upstream portion of the reservoir the dredged sediment contained
more silts and sands than the main body of the lake.
Because of the variable site topography, containment dikes varied from 1.2 to 7 m in
height. The dikes were originally wide enough to drive around on top, but wave erosion
during the prolonged dredging project subsequently made them too narrow for driving in
some areas. Toe drains were required in some areas to control seepage. The containment
area provided 7 to 14 days of water retention, and was compartmented with outlet
structures at different locations for flexible operation, since the slurry pipe would enter at
different areas depending on the place the dredge was working. Supernatant met the 15-
mg/L effluent standard for suspended solids about 75 percent of the time, problems
occurring primarily when it was windy. Emergent wetland vegetation began to grow as
some of the compartments filled with sediment. It was found that by routing the
supernatant through these shallow vegetated areas prior to discharge, the effluent
turbidity levels were greatly reduced, resulting in turbidities on the order of 1 to 2 mg/L
for prolonged periods. Supernatant from the containment area was discharged back into
the reservoir. In addition to the development of wetland vegetation, the containment area
cells saw extensive use by waterfowl. At the completion of dredging, the containment
area was allowed to dewater and consolidate for 2 years, by which time it was suitable for
agricultural use. The land was then leased to a local farmer for the production of corn and
soybeans (Skelly, 1996).
The project began in 1987 and required 4 years to complete. A total of 2.28 Mm
3
was
dredged at a unit cost of $3.02/m
3
($2.31/yd
3
), which included the cost of purchasing and
constructing the containment area. Project characteristics are summarized in Table 16.2
and costs are summarized in Table 16.3.
16.5.2 Valdesia Reservoir, Dominican Republic
The concrete-gravity Valdesia Dam, a hydropower facility owned by Corporación
Dominicana de Electricidad, was constructed in 1976 approximately 80 km west of Santo
Domingo. Two hurricanes damaged the dam and deposited large volumes of sediment,
which prompted subsequent dredging operations. Information for this example is based
on a site visit in November 1990, including discussions with engineers and operators.