JOHN BLUNDEN
70
authorities to review such workings with a view to either modifying the consent or
permitting its continuation as before. Few planning authorities used this power until the
Peak Park Joint Planning Authority was faced in the mid-1990s with a situation posed by
Ready Mix Concrete (RMC) which might have inflicted severe damage on the landscape
at Longstone Edge. At their recently acquired quarry at this location, the company
attempted to extract limestone in a situation where the consent had specified that fluorspar
and barytes might be worked along with other minerals, but made no specific reference to
limestone. RMC’s plan to remove 15 ha to a depth of 60 m would not only have produced
19 million tonnes of limestone, but have severely impaired the appearance of the skyline
to the extent that the planning authority decided that it would use its powers to revoke the
original consent. The company at first stated that it would appeal against the decision, but
it has now agreed not to contest it, and showing great pragmatism perhaps in the light of
its wider interests as a leading aggregate producer, expressed its keenness to work with
the Peak Park. Apart from the decision being welcomed by environmental NGOs, the
action taken by the planning authority is being seen as a test case by other National Parks
in England and Wales which currently face more than a hundred similar ambiguous
quarrying consents (Jury 1998; Bent 1998).
This particular problem apart, the extraction of limestone for chemical or aggregate
purposes from its ten active quarries has been a major source of conflict in an area which is
supposed to be devoted to conservation and recreation. However, the largest of these,
Tunstead, near Buxton, which was formerly outside the boundaries of the Park, has been
allowed a major extension into it. The approval of this development was given on appeal
because the national need for high purity limestone for chemical use was considered as
more important than its environmental impact and the designation of the area as a national
park. The quarry came into production in the mid-1980s and over its predicted life of sixty
years it is likely to have an average output of 10 million tonnes per year of chemical limestone,
together with some aggregate material.
As for fluorspar, of which the UK is an exporter, 70 per cent is won within the
boundaries of the Peak Park. When the market was at its most buoyant in the late 1970s
and early 1980s, this mineral, along with barytes, was extracted at a number of sites
some of which were open pit operations rather than underground workings. This in
itself caused widespread damage to the visual qualities of the landscape, as did the
disposal of waste from its primary processing (about 3 tonnes to every one of valuable
material). This was largely accomplished through the provision of tailings ponds where
the wastes, suspended in water as a result of processing, settle out. Even though these
may be ultimately drained and grassed over, they remain an alien feature in the landscape.
However, the environmental situation has recently improved. There are now fewer open
pit operations, with a greater concentration on underground working and with minerals
processing limited to one plant. Moreover, the backfilling of waste, combined with
cement, into the worked-out areas has reduced the need for tailings ponds but not
eliminated them. The only way in which this might be achieved would be to use the
remaining wastes for the manufacture of aggregate materials. Unfortunately, these would
still be produced in quantities well in excess of the needs of local markets (Peak Park
Joint Planning Board 1998).