•
Choose
a
realistic
design period,
but
make
it
possi-
ble
to
meet
flow
demands beyond
the
design period.
•
Design
the
station layout
to
allow
for
planned
increases
in the
capacity
at
specific times within
the
design period.
•
Always
use the
larger pump size when choosing
between
two
sizes.
•
Optimize
the
size
of
force mains.
The
velocity
should
be at
least
0.76
m/s
(2.5
ft/s)
to
keep grit
moving.
At
such
a low
velocity,
a
daily
flush at
1
.2
m/s
(4.0
ft/s)
for an
hour
or
more
is
desirable.
The
maximum
velocity should
not
exceed about
2.4 m/s
(8
ft/s) because
of
high head losses
and the
possibil-
ity
of
water hammer.
Water
Pumping
For the
probable population
to be
served
and the
esti-
mated
flow
needs, choose
a
realistic design period
and
allow
for
future
expansion beyond
the
design period.
• The
station layout should permit plans
for
periodic
increases
in flow
capacity.
•
Carefully
consider
the
maximum daily
and
hourly
flowrates,
the
requirements
for fire flow, and a
com-
bination
of the
two.
• If
head
and flow are
expected
to
change
signifi-
cantly
over
the
years, choose pumps with medium-
sized
impellers
so
that impellers
only
—
not
pumps
—
need
to be
changed
to
match
the flow.
•
Choose
the
correct
pipe
roughness
(or
range
of
roughnesses)
and not a
single "conservative" value
(see Section
3-2).
•
Optimize
the
size
of
transmission mains. Where
velocities exceed about
2.4 m/s (8
ft/s),
water ham-
mer
may
become
a
concern
and may
require addi-
tional, expensive control equipment
and
structures.
Sludge
Pumping
Sludge
is
usually
confined
to
treatment plants
and
transported
for
only short
distances
—
a
few
hundred
meters
or
yards
at
most.
Centrifugal
pumps
can be
used
for
thin sludges
in
large quantities.
But
positive-
displacement pumps
are
usually required
for
thick slud-
ges, because these sludges
are
thixotropic
and,
after
immobilization, high pressures
are
required
to
start
their movement.
For
wastewater sludges, consider:
•
Sludge properties, which
are
entirely
different
from
those
of
water
(see
Chapter
19)
•
Sludge pipelines longer than
1.6 km (1 mi)
must
be
designed
on the
basis
of
measured friction.
(The
associated problems
are
difficult
and
beyond
the
scope
of
this book.
See
Section 19-5.)
•
Comparisons
of
plunger, progressive cavity,
and
lobe pumps based
on
both
first
cost
and
mainte-
nance
•
Pipelines
of no
less than
150 mm (6
in.)
in
diame-
ter,
although glass-lined piping down
to 100 mm (4
in.)
may be
suitable
•
Glass lining
for
sizes below
250 mm (10
in.)
and
cement-mortar lining
for any
size
(but
particularly
for
larger pipe).
Water
plant sludges
are of two
general types:
(1)
those resulting
from
sedimentation
and flocculation
and
(2)
those resulting
from
lime softening.
The
former
are
gelatinous, bulky,
and
difficult
to
dewater.
It may be
desirable (although
difficult)
to
decant
them,
but
they
are not
difficult
to
pump.
The
charac-
teristics
of
softening sludges vary greatly,
and it is
difficult
to
predict
a
conservative design that oper-
ates well over
the
range
of
necessary conditions.
It is
wise
to
•
Choose pumps that
can be
easily
and
relatively
quickly
disassembled
and
cleaned
and
locate them
for
ready accessibility.
• Use
straight
pipelines
that
can be
rodded
out,
or,
better,
use
open troughs that
are
easily accessible
for
cleaning.
• For a
more extensive discussion
of
sludge pumping,
refer
to
Chapter
19.
25-6.
Types
of
Pumping
Stations
The
following discussion about
the
types
of
pumping
stations
is
necessarily abridged. Greater detail
is
given
in
Chapters
11-15,
17-19,
26, and 29 of
this volume,
so
this section
is
limited
to a few
selected
essentials
relating
to
choice. Develop alternatives only
to the
point where realistic, comparative cost estimates
can
be
made (e.g.,
as
shown
in
Example
29-1).
Wastewater
Pumping
Stations
Decisions should
be
based
on the
required capacity,
cost, reliability,
the
owner's preference,
and
aesthetic
considerations. Reliability
is
more important than
effi-
ciency. Sewage pumps must pass stringy materials
and
other
solids,
and it is
frequently specified that they
must
be
able
to
pass
a
75-mm (3-in.) sphere.
But
because many relatively large pumps contain restric-
tions, always require certification
on the
size
of
solids
to be
passed
entirely
through
the
pump.