ECONOMICS 821
These items continue to be developed through most of the construction phase by
a small contractor’s team consisting of one or two process engineers, a mechanical
engineer, and/or a project engineer. These will be discussed later.
The field move in
The extent of the field ‘move in’will depend on the type of construction decided
on, the location of the site, and the proximity of the labor source to site. The most
extensive effort in this respect is the situation where it is decided to utilize direct labor
and this labor source is a considerable distance from site. In this case the contractor
must set up a camp for the labor and field staff complete with canteen, social facilities
and the like. Developing labor contracts also becomes a major activity for both the
contractor and the client in approving these contracts. In this situation there would be
a definite advantage in totally subcontracting the work. This field aspect of the ‘move
in’would become part of the subcontract.
Monitoring the field activities
The activities of the client’s project team during the construction phase is reduced to
monitoring the cost and schedule with respect to the master construction plan. The
team itself will probably be reduced to the project manager and possibly a project
engineer with the process engineer on a part time basis. It is also likely that this smaller
project team will remain in the contractor’s office rather than move permanently to
site. Usually monthly site meetings are conducted and the project manager among
others would attend these meetings. During such meetings physical review of progress
in the field would accompany an in depth written and verbal report on the schedule
and the cost aspect.
Although the project manager would not be present full time on site, there would be
a client presence there continually. Heading this team would be the client’s construc-
tion specialist, with some project engineering assistance. As the construction work
progresses this team would expand to include specialists in all disciplines who will
follow the installation and testing of equipment relating to these various disciplines.
These would include mechanical engineers, electrical, and instrument engineers. The
follow-up for the piping installation would usually be undertaken by piping specialists
(to check such details as piping layout conforming to plan, pipe stress analysis and the
like). Most clients also include the proposed permanent operators and maintenance
staff of the facility in this team.
Final activities of the project team-mechanical completion
The erection of the facilities is considered complete when all the equipment, piping,
cables, buildings (if any) have been installed, and such testing that is necessary (such as
line and vessel pressure testing) has been done. The contractor is also responsible for
completing all insulation, such refractory lining as may be required, and the disposal
of debris from the site. Most vessels may be left open for final inspection by the client.