362
Advanced
Blowout
and
Well
Control
In
late September, 1984, Mobil experienced
a
major blowout at
its N-91 West Venture gas field, offshore Nova Scotia,
Canada.
A
relief
well, the
€3-92,
was spudded approximately
3,000
feet from the blowout.
During drilling
at
2,350
feet with conductor set at
635
feet,
a
gas kick was
taken.
The gas zone encountered was the result of the charging caused by
the N-91 blowout.
A
shallow seismic survey was conducted
to
assist in
defining the extent of the underground charging. Booth reported
that,
when the seismic
data
was
compared with the original work,
two
new
seismic events were identified.' The deeper event occurred at about
2,200
to
2,300
feet, which corresponded
to
the charged zone in the relief well.
However, there was also
a
second event
at
approximately
1,370
to 1,480
feet. The upper interval was interpreted to be approximately
3,300
feet in
diameter emanating from the N-91.
This
event was of great concern since
only unconsolidated sandstones, gravels and clays were present between
the charged interval and the
ocean
floor 1,100 feet away.
Fortunately, the charged interval never fractured
to
the surface.
Eight additional surveys were conducted
between
5
November, 1984 and
9 May, 1985. Those surveys revealed that the gas in the shallow zone
had
not grown significantly since the first survey and
had
migrated only
slightly up dip.
In
addition, the surveys were vital for the selection of safe
areas for relief well operations. Finally, the surveys were vital in
analyzing the safety and potential hazard of continuing operations
onboard the Zapata
Scotain
with the rig on the blowout.
In
the past, it
has
been customary
to
drill vent wells into the
charged zones in an effort
to
reduce the charging. Generally, such efforts
have not proven successful. The zones of
loss are normally not good
quality reservoir. Therefore, the amount of gas being lost greatly exceeds
that
recovered from the vent wells. The result is that the charging
is
relatively unaffected by the vent wells.
At the
TXO
Marshall,
for
example,
three
vent wells were
completed. The blowout
was
discovered to be losing approximately 15
mmscfpd underground. The
three
vent wells were producing
a
total of
less
than
2
mmscfpd. Experiences such
as
this
are commonly reported.
If charging is a problem, the better alternative may
be
to vent the
blowout at the sulface. If charging is to be affected,
the
volume of gas
vented would have to be sufficient
to
cause the flowing surface pressure to
be less than the shut-in surface pressure plus the frictional losses between