
397
in the North Sea, larger and more serviceable equipment that could operate during
the more severe weather conditions became more desirable. Several ships with very
large crane capacity were converted to derrick ships.
In
many cases, the different
wave response to the shipshape hulls did improve working performance over that of
derrick barges. The new generation of semisubmersible derrick barges, which are
used now, offers considerable improvement
in
the ability to work in more hostile
environments (Lee,
1981).
The main structural component of a typical fixed steel platform is the jacket, or
lower unit. This jacket extends from the ocean floor to above the water surface. The
legs (or columns) are open pipe members. Tubular bracing members interconnect
these legs to make the jacket a single rigid structural unit space frame. Piles are
driven through the legs of the jacket into the ocean floor. The jacket serves as a
driving guide during pile installation, and as a structural unit to resist horizontal
loads from wind, waves, and currents. For use in shallow water, the jacket is
completely fabricated in one piece, carried to location
on
a cargo barge, and picked
up and set
on
bottom by a derrick barge.
For use in deeper water, the most frequently used installation technique for
jackets has been launchmg from a barge at the location (Fig.
10-7).
The launch
barge must be of sufficient size for marine stability, and of adequate strength
tu
support the weight of the jacket during tipping. After the jackets are launched, they
must be up-ended (rotated) from the horizontal to a vertical attitude. With the
shallow-water jackets, this is usually accomplished by lifting. Because of the
magnitude of the loads, deep-water jackets must be rotated and set
on
bottom
essentially by controlled flooding. This requires more sophisticated flooding and
venting systems, with appropriate backups, which must be carefully designed and
fabricated. For successful installation of the larger jackets, model tests and detailed
operational instruction, including contingency plans, are essential.
After the jacket has been set
on
the ocean bottom, it is leveled and piling are
stabbed through the jacket legs. When the piling has been driven to the proper
penetration, the deck unit, or units, are lifted into place and set
on
the top of the
piling. The connections between the deck leg and the piling, as well as between the
piling and jacket, can then be made and all other operations necessary to complete
the structure can be performed. After this
“
weld-out’’ process, the drilling rig
and/or any other packaged equipment modules are set
on
the structure. This
method
of
construction has been developed to best utilize the capabilities
of
offshore construction equipment and to minimize erection time at the location. The
critical period between launch and “weld-out’’ must be kept to a minimum (Lee,
1981).
The concept of a self-floating jacket is a viable alternative when deep-water
jackets are too heavy for available launching equipment. Self-floating jackets have
been used about two dozen times compared to hundreds of barge-launched jackets.
The self-flotation structure is characterized by legs which have a sufficiently large
diameter
so
that adequate “built-in” buoyancy is provided. This enables the jacket
to float at a relatively shallow draft. Because this buoyancy is built into the jacket
(rather than into the launch barge), more steel is usually required.
In
addition, the