
391
The two types of feasible buoyant structures are: (1) the guyed tower, and (2) the
tension-leg platform. Semisubmersibles can also be converted into production
platforms; however, they are very sensitive to topside loading. This is as well true of
the other buoyant-type structures to some extent. The latter, however, are generally
larger and rest on the seafloor, which provides additional support, and therefore,
can support the required production facilities.
The guyed tower is a slender-trussed structure that rests on the
seafloor, with guylines holding the structure in place. The tower transmits the
primarily vertical gravity loads imposed by the drilling and production equipment
mounted on the surface decks to the seafloor. There are two ways of providing
support for the tower at the seafloor. One is by the conventional piled foundation.
The second means of anchoring the guyed tower is by pure gravity: the base is
implanted in the seafloor using a vertical bearing foundation consisting of a
truss-reinforced stiffened shell called the “spud can”. In the latter case, long-term
settling of the tower can be a problem. This is avoided by preloading the structure
during installation. In the final stages of tower installation when the tower has been
installed in an upright position, the spud can is artificially forced into the ocean
bottom until the desired load-carrying capability is reached. Drilling mud is pumped
into the spud can in order to achieve this purpose; thereafter, the mud is pumped
out. The well conductors penetrate through the spud can.
The guyed tower (Fig. 10-12) is a relatively simple structure and is not difficult to
fabricate. It is not very heavy and its movement (sway) is within satisfactory limits.
Horizontal support for the guyed tower is provided by 12-24 wire-rope, synthetic
material, or chain-type cables called guylines (Dunn, 1980). These guylines are
secured on one end to the bridge strands arranged symmetrically around the tower
by means of pairs of wedge-type Lucker clamps. The guylines run downward from
these bridge strands to the fairleads kept about
50
ft below the mean water level
so
that they are below the keel of passing vessels. Through these fairleads, the guylines
run further on to clump weights on the seafloor. Beyond the clump weights, the
guylines run to either anchor piles or to conventional drag anchors.
The cable tension is controlled through the Lucker clamps and a hydraulic
jacking system. The tower is designed to give a maximum tilt of
2”
or less during
expected storm conditions. In moderate seas, the clump weights remain on the
seafloor and keep the guylines in a taut condition. Under extreme storm conditions,
the design-allowable tower oscillations may be exceeded, and once they become too
large, the clumps will gradually lift
off
the seafloor, softening the guying system and
further endangering the structure.
The guyed tower is simpler and cheaper to construct and requires only conven-
tional fabrication equipment and techniques. Its installation, however, is quite
sophisticated and complex, particularly with respect to the guylines, clumps, and
anchor piles (Anonymous, 1981). The guyed tower also is relatively cost-insensitive
to increased water depth. There are, however, some cost increases with depth:
mooring costs and maintenance costs increase with water depth and remoteness.
Fig. 10-13 shows the installation of the guyed tower-type Lena platform in the
(1)
Guyed
tower.