ICOLD Bulletin **:
The Specification and Quality Control of Concrete for Dams
Revision 7.0
56 of 71
March 2006
8.2.5
Official reporting
The test and inspection report distribution diagram is shown in Figure 4. There are two types of
testing: field and laboratory. Field test occurs during concrete or RCC placement. Field
technicians perform a series of tests, record the test results, and inform the field inspectors.
Laboratory tests are performed in the on-site QC laboratory. The Laboratory Manager reviews
the test data before entering in the computer database. The computer database recalculates and
stores the test data. The original test data are filed and at the end of the job these documents will
go to Document Control. At the end of the day, the Laboratory Manager generates reports for the
inspectors. Every week, the Laboratory Manager generates test reports. The Resident Engineer
reviews the reports. After reviewing, the reports the reports are distributed to the Project
Manager, DSOD, the Design Engineer and the Owner.
When inspector observes that the contractor’s work complies with the project specification, the
inspector writes a Daily Field Report (DFR). The DFR is then reviewed by the Lead Inspector
and the Construction Manager. When the inspector observes deviations from the project
specification, a non-compliance report (NCR) is generated and issued. The non-compliance
report is distributed to the responsible party for the non-compliance report for evaluation and a
recommended disposition. The Resident Engineer and Design Engineer review the recommended
disposition. Upon approval from the Resident Engineer and/or Design Engineer, the Contractor
conducts the corrective action. The inspectors verify the completion of the corrective action and
issue a closed NCR. The NCR is reviewed by the Construction Manager, Resident Engineer,
Project Manager, DSOD, and the Owner. If the NCR has modified the design documents it is
then posted as a design change.
8.2.6
Tracking of concrete strength
Figure 5 shows the chart developed to track the strength of the RCC built into the dam. The chart
shows that the control of strength at 365-day maturity can be classed as good with a coefficient
of variation of 12.9%. The results of the tests on specimens subjected to 7-day accelerated cure
are shown to be a good guide to the 365-day strength. The coefficients of variations increase
with lesser maturities and this is typical of high fly-ash mixes.
8.2.7
References
Tarbox, Glenn S., Michael F. Rogers, David E. Kleiner, and Gerard E. Reed, III,
Olivenhain
Dam Design,
Roller-Compacted Concrete For Dams And Dam Rehabilitation, International
Seminar and Construction Tour, San Diego, California, 2002.
Ehasz, J., H. Ehrlich, M. Pauletto, J. Reed, K. Steele, and G. McBain,
Partnering For Success At
the Olivenhain Dam
, Dams – Innovations for Sustainable Water Resources, 22
nd
Annual
USSD Conference, San Diego, California, 2002, p. 389- 397.
Tarbox, Glenn S., Malcolm Dunstan, Russ Grant, Tom Reynoldson, and James Stiady,
Supplementary Olivenhain Dam Trial Mix Program,
Dams – Innovations for Sustainable
Water Resources, 22
nd
Annual USSD Conference, San Diego, California, 2002, p. 271-
285.
Holderbaum, Rodney., Robert A. Kline, Jr., Michael F. Rogers, Randall J. Hartman, and Russell
Grant,
Design of Roller-Compacted Concrete Materials for The Olivenhain Dam
, Dams –