ICOLD Bulletin **: The Specification and Quality Control of Concrete for Dams
Revision 7.0
25 of 71
March 2006
For RCC, lift thickness is normally specified as well as the method for ensuring monolithic
construction within each lift. The same applies to conventional mass concrete, but here the layer
thickness within each lift is also specified. To eliminate the risk of segregation at the base of a
lift, particularly with large MSA and lean mass concrete, a bedding mix with a lesser MSA and
possibly a higher cementitious content may be required.
Tests for concrete consistency (slump or VeBe test for RCC) as well as concrete temperature at
the point of delivery may be required along with acceptance criteria. The acceptance criteria will
include allowable variations in measured properties and grounds for rejection of concrete as
unsuitable.
4.2.2 Inspection
Control of the concrete placement by inspection is essential to ensure that the required end
product is achieved. The concrete is normally inspected at the point of delivery to the site and at
discharge into the form. Inspection is a visual check on the appearance of the concrete where
workability, uniformity and conformity with established appearance are important. Deviations
suggest that something is wrong with the mixture and that corrective action is required.
In some circumstances it may be necessary to adjust the workability of concrete at the placement
by the addition of water while it is in the transit mixer. This is an acceptable practice providing
the specified water-cement ratio and the total allowable water in the mix are not exceeded.
However, this adjustment should not be necessary in a well controlled concrete manufacturing
process. Unusual loss of workability is commonly a sign of problems in the system or with the
materials.
Good communications between the point of placement and the batch plant are essential. Any
undesired changes in fresh concrete properties at the placement have to be acted upon and
corrections made to the mixture at the batching and mixing plant.
Working procedures have to be followed and verified by the inspectors. Important factors are
correct placement procedures (lift thicknesses, set-backs of successive lifts, elimination of rock
pockets) and consolidation procedures (depth and time of vibration, uniformity of treatment) and
conformity of equipment to specification requirements. Verification of the adequacy of the
curing method and time is important.
4.2.3 Testing at time of placement
The purpose of routine control tests is to check and confirm the properties of the fresh concrete
such as temperature, workability, and air content, and immediately make any adjustments that
are necessary. These tests should be run on the first batch out of the plant and randomly during
each shift or placement or whenever change is observed in the appearance of the concrete.
Inspectors can quickly learn to visually judge the consistency or workability of the concrete as
delivered to the placement. These inspectors should be alert to any changes and to notify the
batching/mixing plant immediately when concrete characteristics are not as they should be. This
requires effective and reliable communications equipment, either radio or landlines.
Testing is performed at time of placement to ensure that the concrete has the appropriate
workability, temperature, compacted density and air content. When delivery to the site is by
truck, the concrete is commonly tested before it is discharged to avoid the risk of removal of
non-conforming concrete from the placement. Workability is measured with the slump test for
conventional mass concrete. For low workability (zero slump RCC) mixes the Loaded VeBe test
is normally employed (other tests are in use in some countries). The Loaded VeBe time also is
dependent on the test equipment vibration frequency (function of the site power supply),