
I
r
t
I
tunnels were
closed
in stages, after
these
had
served
the
diversion
requirements.
The
tunnel P3 was closed
for
second
stage
works, that
is, completion
of bulkhead
reach and
installation
of emergency
gate
in
October
1971. This tunne!
was re-opened
as
gated
tunnel
in
June
1972
for
passing
river
flows. Tbe
river bed
entries
of the
T-tunnels and
P-tunnels
(Pl
and P2 only),
were
closed
by
lowering stoplogs
in
the
upstream
portals
during September
1972
and October
1973
respectively
for
taking up
permanent
closure
plugs
and
second
stage
works. The
final
closure of P3R tunnel
for
conversion
into
penstock
was
planned
by
lowering
gate
through
bulkhead shaft with the
reservoir level at
El. 384.05
m. For
this
purpose,
a lined
construction
of
size
3.05
m
x6.40
m was constructed
in
the
tunnel.
However, during
operation
of
the
restricted
P3R
tunnel,
the
liners
provided
in the
bulkhead
reach
got
ripped
off
due
to high
velocity flows. It was,
thus
not
possible
to
block
the river bed
entry
of P3R
tunnels,
as
originally
planned.
The
final closure
of
P3R tunnel
was,
therefore, affected
by
lowering
stoplogs
in
the
upstream
portal
under
53.3
m deep
water with
the
help
of
divers and
derrick crane
in June
L976.
Lowering
of
stoplogs under
53.3
m
deep
water
was
an unprecedented
job
and
was
accomplished
by
meticulous
planning
and
devising facilities
necessary
for
successful
closure
of the
tunnel.
2. CONSTRUCTION OF DAM
The
construction of
dam involved
the
placement
of
nearly
35 million
cu
m
of
fill
materials
and about
nine
million cu m of excavation of
river
bed meterial
and
rock.
Tbis
was
a
stupendous
task
and required
thorough
pre-planning
of all operations, including
selection of equipment, facilities
to keep
the equip-
ment
in
good
working older,
arrangement
of spares,
tyres, fuels,
lubricating
oils, etc.
Section
of
Dam
Section
of the
dam and its
zoning
was
designed
to
facilitate
the
maximum
use of the materials
avai-
Iable
from excavation
of
various
appurtenant
works,
yfu.,
spillway,
tunnels,
approach
channels,
stilling
basins,
etc.,
for impervious core and
natural
river bed
deposits
for
filter
and
pervious
zones.
The final
maximum
section of
the
Beas
Dam
with
zoning
arrangements
as adopted,
is
given
in
Figure
6.
The
main
embankment of
the
dam
was
divided
into the
following
fill
zones
(f)
Iurnnvrous
Zolre
This
zone
comprised earth from stockpiles
of
materials
excavated
from
various
structures or
directly
from
excavation
of
foundations.
la-The
material
for
this
zone
was
primarily
the
clay
shale
containing
less
than
50
percent
sand
rock.
210
Ib-The
material
for
this
zone
was
primarily
the
sand
ro-ck
containing
less
than
-50
percent
clay
shale.
core.
(ff)
Prnvrous
ZoNr
This
zone
included
2a-Filter
zone
of selected
free
draining sand
and
gravel
wifh
not more
than l0
percent
of size
l.a-rger
than
75
ffiD,
but material
exceeding
150
mm
was
not
permitted.
2b..
Pervious
zone
of
selected
free
draining sand,
gravel,
cobbles
and
boulders. The
maximum
size
of
the
material
used
was
such that
no
stone
protruded
above
the
compacted
lift
of
0.6 m.
Rip-rap
of selected
gravel,
cobbles
and
boulders.
Upstream
and downstream
toe
weights of
random
material.
Excavation
and
Treatment
of Foundation
(i)
ExcevArloN
About
nine
million
cu
m
of excavation of river
bed
material
and
rock
was
involved
for foundations
of
the
dam.
In
the
river
portion
under the shell
zone
of the dam
embankment,
the
excavation
was extended
to
clean
sand;
gravel
and
cobble material having
same
characteristics
as
that
of
shell zone material. Tbe
excavation of
core
trench
on right
abutment
was
taken
up to
a
minimum
depth
of
6
m
below the
actual
bed
rock level
or to
the sound rock
level
whichever
was
lower.
However,
this criteria
was
dispensed
with
as
it was
considered
that no useful
purpose
was
served
by
excavating
the
sound
rock
first
and
then replacing
it
with the
same
material.
In
the
river
bed
portion,
the core
ftench
excavation
was, therefore,
extended
to sound
bed rock
only. The
key
trench was,
however,
excavated
6 m below
the
bottom of the
core
trench.
The
excavation
work
commenced
in
October
1965,
when the
excavation
on the right
abutment
was
taken