15 Planning, operation and economics of wind farm projects 493
- For variable-speed wind turbines with pitch control the portion of the
costs of generator and control increase.
In addition to the production costs, the total wind turbine investment costs include
share the design and development costs, the profit and further costs attributable to
warranty, transport and erection.
The other portions of the total investment costs mentioned in Fig. 15-8 are influ-
enced to a large extent by local site conditions such as the wind farm project size
(single wind turbine or wind farm), the type of soil and the distance to the grid-
connection point. Therefore, when comparing economically efficient wind farm
projects of the same size there will always a spreading of the actual project costs
be observed.
The grid connection costs are often the second-biggest investment cost factor,
Fig. 15-8. These vary strongly according to local conditions, i.e. the distance to the
next grid-connection point, and the requirements of the local grid operator as well.
The German Renewable Energy Sources Act (EEG) provides an unambiguous
definition as to whom the costs are to be allocated. Basically, the grid connection
costs are borne by the wind farm operator.
However, if the local grid is too weak for the planned wind farm capacity the
grid reinforcement costs have to be borne by the grid operator who is legally
obliged to permit wind power feeding. Therefore, the grid reinforcement costs do
not form part of the investment cost estimation.
Table 15.3 Cost structure of wind turbine components and assembly , typical values according
to [4, 5]
Rated power 600 kW 1,200 kW Typical span
Component € Share
in %
€ Share
in %
of cost share
in %
Gearbox and coupling 80,400 21.8 115,000 18.1 10 to 25
Rotor blades 63,800 17.3 150,000 23.6 15 to 25
Tower (incl. coating) 58,000 15.7 150,000 23.6 12 to 25
Generator and control 43,800 11.9 65,000 10.2 10 to 20
Nacelle frame and
yaw bearing
31,600 8.6 35,000 5.5 5 to 10
Hub and main shaft 29,000 7.9 40,000 6.3 5 to 10
Housing 16,600 4.5 18,000 2.8 2 to 5
Cables and sensors 13,400 3.6 18,000 2.8 2 to 5
Hydraulics 11,600 3.1 15,000 2.4 2 to 5
Yaw system 8,700 2.4 10,000 1.6 1 to 3
Assembly 11.600 3.1 20,000 3.2 2 to 5
Total 368,500 100.0 636,000 100.0
614 €/W 530 €/kW
Remark: The total wind turbine investment costs include additionally R&D
costs, risk, profit, warranty, transport and erection