was, of course, at the expense of significant negative phase sequence currents
flowing in the generators and associated heating and losses, although in this wind
farm nuisance tripping was not reported. The wind farm slightly reduced the
voltage flicker measured at the point of connection using a flickermeter. This was a
complex effect with the generators raising the short-circuit level but also introdu-
cing fluctuations in current. There was a slight increase in total harmonic voltage
distortion with the wind farm in operation, mainly caused by a rise in the fifth and
seventh harmonics when the low-speed, high-impedance winding of each generator
was in service. This increase was probably associated with a parallel resonance of
the high-impedance winding of the generators and the power factor correction
capacitors and the high levels of ambient harmonics on the utility network. The
most significant transient event was the energization of the entire wind farm
including 24 turbine transformers, but without the wind turbine s connected. This
led to a transient 8 percent dip on the 33 kV voltage. Energization of the wind farm
in this manner is rare and occurs only after disconnection by the grid interface
protection.
Davidson identified three main sources of power fluctuation: wind turbulence,
blade passing, and blade pitching. The major effects were found to be at wind
speeds of 9–10 m=s, mainly due to wind turbulence, and above 20 m=s due to
blade-pitching effects, although the pitch control on these turbines was not com-
pletely effective in high wind speeds. The highest wind speeds (. 20 m=s) led to
the greatest flicker. As might be expected siting turbines in turbulent locations
significantly increased power fluctuations. Individual wind turbine starts/stops
and speed changes made little impact on network voltage flicker.
These results are typical of the experience of connecting wind farms, with a large
number of relatively small induction generators, on to rural distribution circuits. In
a number of studies some aspects of power quality have been shown to be
improved by the effective increase in short-circuit level. However, the effect of
embedded generation plant on distribution network will vary according to circum-
stances and each project must be evaluated individually. In particular, the connec-
tion of large single generators, as opposed to a group of smaller generators, may be
constrained by consideration of flicker.
Craig (1995) undertook a similar investigation on another WEG MS3-300 wind
turbine connected to an 11 kV network in Northern Ireland over a 2 month period.
A particular feature of this study was the very low network short-circuit level
which varied between 8–15 MVA on the 11 kV point of connection depending on
how the 11 kV utility circuits were arranged. The X=R ratio of the source imped-
ance was approximately 0.5 illustrating the highly resistive nature of the long 11 kV
overhead circuits. The site had a mean wind speed of 9 m=s and a turbulence
intensity of 12.5 percent. Measurements were taken to investigate the voltage
disturbances due to wind turbine starts (with and without an anti-parallel thyristor
soft-start), steady-state voltage variations, dynamic voltage variations and flicker
and also volta ge unbalance.
The conclusions of the study were that, under certain circumstances (particularly
high wind speed cut-out and connection without the soft-start) the dynamic voltage
variations excee ded recommended limits. Steady-state voltage variations could be
predicted reliably from load-flow calculations and were within limits. The wind
POWER QUALITY 585