1000 MW. The generation voltage is rather low (typically around 20 kV) to reduce
the insulation requirements of the machine windings and so each gene rator has its
own transformer to increase the voltage to that of the transmission syst em. The
transmission network is interconnected, or meshed, and so there can be many paths
for the electrical power to flow from the gen erator to the bulk supply transformers.
The bulk supply transformers are used to extract power from the transmi ssion
network and to provide it to the distribution networks at lower voltages. Practice
varies from country to country but primary distribution voltages can be as high as
150 kV. Distribution networks are normally operated radially with a single path
between the bulk supply transformers and the loads. In urban areas with high loads
the distribution networks use large cables and transformers and so have a high
capacity. However, in rural areas the customer load is often small and so the
distribution circuits may have only a limited capability to transport power while
maintaining the voltage within the required limits. Most wind farms are connected
to rural, overhead distribution lines. The design of these circuits tends to be limited
by consideration of voltage drop rather than thermal constraints and this severely
limits their ability to accept wind generation.
10.4.2 Embedded generation
In the early days of electricity supply, each town or city had its ow n generating
station supplying the local load. Thus all generation was local and embedded into
the distribution ne tworks. This arrangement suffered from two major problems: (1)
the generating sets were rather small and hence of low efficiency, and (2) each
station had to keep an additional generator running in case of breakdowns. Then in
the 1930s it was found to be techni cally possib le and cost-effective to interconnect
these individual power stations so that larger, more efficient generating sets could
be used and the requirement for reserve generation could be reduced. Over time,
the size and voltage of the interconnected grid networks increased and so now
voltages of 400 kV and even 765 kV are common and a single grid connects most of
continental western Europe. There have also been significant advances in the
technologies of central generating plant and, for example, large modern combined
cycle gas turbine (CCGT) generating units have efficiencies approaching 60 percent.
However, over the last 10 years there has been a resurgence in interest in
embedded generation stimulated by the need to reduce gaseous emissions from
generating plant. Three major themes may be iden tified: (1) increased development
of combined heat and power (CHP), (2) exploitation of diffuse renewable energy
sources, and (3) deregulation of the electricity supply industry and the separation
of generation and supply of energy from the operation of transmission and
distribution networks.
CHP plants operate at very high overall thermal efficiencies and so reduce the
total fossil-fuel co nsumed and hence the gaseous emissions. In addition to the
existing commercially available technologies there are major development efforts in
very small CHP generators for domestic use and also in the application of fuel cells.
Primary distribution circuits can accept power injections of up to 100 MW and so
most on-shore wind generation is likely to be embedded in a distribution system.
EMBEDDED (DISPERSED) WIND GENERATION 569