The automation of magnetic particle inspection is often necessary to permit inspection at the required production rate.
Loading, processing, conveying, rotating or manipulating, demagnetization, and discharge can all be automated, which
results in consistent and effortless processing. The inspector can devote all of his time to actual visual inspection while
the machine performs the other functions. Production rates are achieved by having the various functions performed
simultaneously at different stations. Where applicable, the cost of automatic equipment can be justified when compared to
the number of manual units needed for similar production rates.
The cost and time required for manual inspection can be a factor in automating the process. For example, in billet
inspection, everything is automated except the actual visual inspection and marking of imperfections. Manual processing,
inspection, and handling of such a product would be extremely costly and would not satisfy the production requirements.
The use of automated magnetic particle inspection for bearing rollers, bearing rings, small parts, small castings, large
couplings, crankshafts, and steel mill billets is discussed in the following sections.
Bearing rollers are produced at substantial rates, and when magnetic particle inspection is required, it must be
conducted at a rate compatible with production. This usually requires automation of the process in such a manner that the
various stages are performed simultaneously at individual stations.
The contact method is commonly used for inspecting finished rollers for seams, quench cracks, and grinding cracks. This
may involve either the continuous or the residual method, depending on roller material and inspection requirements.
One design of automated equipment for inspecting bearing rollers by the continuous magnetization method incorporates
an indexing-turntable arrangement and utilizes two inspectors. The various functions--magnetization, bath application,
inspection and demagnetization--are performed simultaneously at the various stations. Each inspector visually inspects
the previously processed roller in the fixture, and the roller is removed and placed on the demagnetizing cradle (if
acceptable) or disposed of (if defective). The inspector then places a new roller in the fixture for subsequent processing
and inspection by the other inspector. Acceptable rollers are automatically stripped from the cradle in tandem,
demagnetized, and unloaded into or onto a suitable container.
The production rate of the unit described above is approximately 1000 parts per hour. A similarly designed unit, based on
the residual method, utilizes four inspectors and has a capacity of 2000 parts per hour. The residual method permits the
use of a magnetizing-current shot of very short duration (approximately 50 ms). This minimizes the heat generated at the
points of contact by the flow of magnetizing current.
Where inspection requirements do not allow electrical contact with the rollers due to the fact that any heat generated at
the points of contact is objectionable, production units based on the induced current method can be used.
Bearing rings can be completely inspected by a two-step process involving both a central conductor and induced
current. The noncontact nature of both magnetizing techniques can be very desirable when highly polished surfaces are
present.
This process utilizes automatic equipment for bearing-ring inspection on a high-volume basis. The design is based on a
multiple-station, fixturized, indexing conveyor. The fixtures are combination laminated poles and central conductors. In
both magnetizing methods, magnetizing current is direct current with quick break, and the wet-particle residual method is
employed.
A bearing ring progresses through the unit in the following sequence:
1. Load
2. Magnetize using a central-conductor shot
3. Apply bath
4. Visually inspect for transverse indications
5. Replace on fixture
6. Magnetize using induced current
7. Apply bath
8. Visually inspect for circumferential indications
9. Place on gravity chute for final roll through ac demagnetizing coil and discharge