
Paper F5: Performance management
122 Go to www.emilewoolfpublishing.com for Q/As, Notes & Study Guides © EWP
$
Material held in inventory (scrap value) 3,600
New purchases (500 × $10)
5,000
Total relevant cost of Material Y 8,600
2.2 Relevant costs of labour
The relevant costs of a decision to do some work or make a product will usually
include costs of labour.
The relevant cost of labour for any decision is the additional cash expenditure (or
saving) that will arise as a direct consequence of the decision.
If the cost of labour is a variable cost, and labour is not in restricted supply, the
relevant cost of the labour is its variable cost. For example, suppose that part-
time employees are paid $18 per hour, they are paid only for the hours that they
work and part-time labour is not in short supply. If management is considering a
decision that would require an additional 100 hours of part-time labour, the
relevant cost of the labour would be $18 per hour or $1,800 in total.
If labour is a fixed cost and there is spare labour time available, the relevant
cost of using labour is 0. The spare time would otherwise be paid for idle time,
and there is no additional cash cost of using the labour to do extra work. For
example, suppose that a new contract would require 30 direct labour hours,
direct labour is paid $20 per hour, and the direct workforce is paid a fixed
weekly wage for a 40-hour week. If there is currently spare capacity, so that the
labour cost would be idle time if it is not used for the new contract, the relevant
cost of using 30 hours on the new contract would be $0. The 30 labour hours
must be paid for whether or not the contract work is undertaken.
If labour is in limited supply, the relevant cost of labour should include the
opportunity cost of using the labour time for the purpose under consideration
instead of using it in its next-most profitable way.
Example
A company is considering the price to charge for a contract that will require labour
time in three departments.
Department 1. The contract would require 200 hours of work in department 1,
where the workforce is paid $16 per hour for a fixed 40-hour week. There is
currently spare labour capacity in department 1 and there are no plans to reduce the
size of the workforce in this department.
Department 2. The contract would require 100 hours of work in department 2
where the workforce is paid $24 per hour. This department is currently working at
full capacity. The company could ask the workforce to do overtime work, paid for at
the normal rate per hour plus 50% overtime premium. Alternatively, the workforce
could be diverted from other work that earns a contribution of $8 per hour.