26 DECEMBER 2009 INTERNATIONAL WATER POWER & DAM CONSTRUCTION
PUMPED STORAGE
programme called for the plant to be operational by 2015. However,
within months of the studies getting underway, the data from the
initial drill tests showed the strata to be unsuitable to host the pow-
erhouse and six large storage galleries.
Riverbank announced the project was cancelled in August –
only two months after the Federal Energy Regulatory Commission
(FERC) had issued a preliminary permit and cleared the way for
a priority application.
PORTFOLIO PLANS
With progress ongoing at Wiscasset, and despite the Sparta set-
back, Riverbank Power Corp is pushing ahead with its plans to
develop a range of sites in North America that will result in a
portfolio of 1GW facilities.
The company has looked at more than 50 possible sites in North
America and continues with the work. So far, Riverbank has found
15 sites that meet its initial selection criteria, and disclosure of can-
didate sites will only be announced when sufficient progress is made,
including planning support. Its main areas of focus are the northeast
US and Canada.
There are four main criteria Riverbank uses for an early judgment on
the development potential – geology, hydrology, distance to transmis-
sion grid and community support. Passing these criteria enables disclo-
sure of a candidate project site, and then in-depth studies commence
with drilling and testing into the bedrock, environmental assessment
and evaluating the energy market and transmission capacity.
Riverbank aims to develop five of the pumped storage plants over
the next few years. While originating in, and focused on, North
America, Riverbank would also consider developing project in other
countries, said Kuo-Bao Tong, project manager of the Wiscasset site
and who also helped oversee early development progress on the other
candidate sites.
References
New Opportunities for Pumped Storage – Amler, P.; Hydro 2009
Assessment of Waterpower Potential and Development Needs – Electric
Power Research Institute (EPRI), 2007
Preliminary Assessment of US Water Power Potential and Development
Needs – Dixon, D.A., Bahleda, M., and Adonizo, M.A. Hydro 2009
Influence of the Market Structure on the Installed Capacity of Pumped
Storage Plants – Surla, D. Hydro 2009
IWP& DC
One of the earlier proposals to excavate an underground reservoir for a grid-scale
pumped storage project in the US was to have been at Mt Hope, in New Jersey. The
plant was initially conceived as a 2GW facility. A more minor endeavour, in size if not
ambition for its replicability, was the concept for distributed, or modular, pumped
storaget (DPS) systems, such as that envisioned for the 200MW Brink project, in Utah.
The Mt Hope scheme would have called for one of the largest underground excavations
in the US and was to operate with closed loop water circulation between the grid of
tunnel galleries and the upper reservoir, which would fluctuate 33.5m in level.
A key strength of the Mt Hope project, on a mining property owned by Halecrest,
was its proximity to a power pool serving Pennsylvania, New Jersey and Maryland.
It was to be a 2GW facility, employ pump-turbine/generator-motor technology that
was faster than then used in the US, handle more load demands (up to 20 mode
changes daily) and provide faster response to dispatch calls.
The broad idea for such a scheme was conceived in the 1970s. Halecrest
submitted a licence application to the Federal Energy Regulatory Commission
(FERC) in 1985. Three years later it formed a subsidiary to take forward the
plans, and then set up a partnership, Mt Hope Waterpower Project (MHWP), with
Scandinavian companies in 1990. The general partner was My Hope Hydro, Inc,
and it was also project manager.
The project was aimed to bring more of the advanced pumped storage systems to
the country, it was said, by drawing upon the concept of the Dinorwig power plant,
in Wales, although lessons from Northfield Mountain in the US were also to be
employed. A key difference, though, was that Mt Hope did not have to optimise
location and topography to obtain the highest head possible.
The upper reservoir was to be a bunded structure. The lower reservoir was to
be excavated about approximately 760m below the ground surface, and the
powerhouse and associated caverns were to be deeper still. The arrangement
would provide for 732m minimum net head in generation mode and 810m
maximum head in pumping mode, respectively. The power output of each of the six
pump-turbines was to be 339MW and input for pumping was 368MW, respectively.
A four-year development licence was obtained in 1992, and concurrent with the
award Kvaerner bought Mt Hope Hydro, Inc. The firm would supply pump-turbines
and other firms involved were ABB to provide generator-motors and contractors
included Stone & Webster and Atkinson Construction. The plant was to be brought
online by 2002.
However, the planned start on construction in 1994 was repeatedly rescheduled
by FERC to 1996 and 1999 – when Australia-based Pacific Energy with Macquarie
Bank received Kvaerner’s interest as part of a larger package of assets to
be handled by their new associate firm Atlantic Pacific Infrastructure Ltd. But
legislation was needed to extend the deadline to 2002, and when construction
hadn’t begun by 2005 the licence was terminated by FERC.
A fresh application was made in 2006, seeking a three-year preliminary permit.
The project by then was described with the lower reservoir at approximately 880m
depth and to be associated with the inactive Mt Hope Mine. The powerhouse level
would be slightly deeper still, and five pump-turbines were planned for the facility,
still listed as 2GW. But soon after, still in 2006, the application was dismissed by
FERC, which wanted a ‘cooling off’ period after the hydro power site had been tied
up with one entity for years without work starting.
The project plan was re-thought and FERC received a new application, in 2007, for
a smaller, 1GW facility that was to be developed in four stages and have, in effect,
four pumped storage plants. Pacific Energy, with a 74% holding in the venture, said
it would seek a joint venture industry partner to advance the project.
The new concept envisaged having underground reservoirs within mine-linked
caverns at three levels – depths of 300m below the ground surface, 520m and
760m, respectively. There was to be operational overlap between these staged
upper and lower reservoirs. The scheme also proposed separate powerhouses,
each with a 250MW unit, again at three different levels – depths of 400m,
610m and 850m.
FERC denied the permit application, citing problems with unpaid fees due over the
years when considering regulatory compliance matters.
The Mt Hope land is now host to a 33MW biomass project being developed by
Pacific Energy.
While the last pumped storage scheme for Mt Hope conceived of a cluster of
smaller projects, in effect, the plan drawn up by US renewables venture firm Energy
Unlimited for the Brink pumped storage facility was always for relatively small-
scale, in comparison. The project and the more general, modular-style DPS system
were concepts envisioned in the mid-1990s by the enterprise, although some
other firms were exploring the field.
Energy Unlimited pursued the project with rights having been brought over from
LB Industries, which in late 1995, as permittee of Brink, notified FERC it had
surrendered its preliminary permit for the scheme. The development plan was
to have DPS at the Brink project, including constructing a lower, underground
reservoir that a powerhouse sat alongside in a 76m deep concrete caisson.
The shaft was to house two single-stage reversible Francis units, and it would
operate about 10 pumping-generating cycles per day under net head of 262m.
Water was to be circulated in the closed system, and Brink was planned to be
operational by 2000.
However, market economics put a halt to the scheme: prices were too weak;
the well established gas-fired generation sector enjoyed too much of market
dominance despite DPS costs coming to within its range; and, utilities were wary
of commitments in light of uncertainties in how deregulation would play out.
Closed Loop pumped storage proposals