SUMMARY
OF PRINCIPAL
FEATURES
Location
On
the Colorado River
17 miles
(27,2
km)
upstream from
Lee
Ferry, Arizona
Purpose
Power, water
supply,
recreation
Owner
Bureau of
Reclamation
Engineering
Bureau
of Reclamation
Construction
Merritt-Chapman
and
Scott Corp.
Chronology
Construction
period:
195?-1964
Commercial
operation: unit l-September 1964, unit 8-
February
1966
Reservoir
Total capacity
to elevation 3,700 ft
(1.128
m):
ac-ft
(m3
x 1ff) ------- 27,000,000
(33.305)
Active capacity:
ac-ft,
(m3
x 106)
20,876,000
(25.75t)
Surface
area:
acres
(m2
x
10r) ---.----.
161,400
(65.317)
Dam
Type:
Concrete
arch
Dimensions-ft
(m):
Structural
height
710
(216)
Top
width
25
(7,6)
Maximum base width
300
(91,4)
Crest
length
1,660
(476)
Crest
elevation
3,715
(1.132)
Total volume:
cu
yd (m3)
------------ 4,901,000
(3.747.000)
Spillways:
One
concrete-lined
tunnel spillway
in
each
abutment
controlled
by
two
40-ft
(12-m)
by 52.5-ft
(16-m)
radial
gates
Elevation top
of
gates:
ft
(m)
--
3,700
(1.127)
Crest
elevation:
ft
(m)
3,648
(1.119)
Capacity
at
elevation
3,?11
ft
(1.131
m):
cfs
(m3lsec)
276,000
(7.815)
Outlet
rvorks: Four
96-in.-diam
(243,8-cm)
pipes
each
con-
trolled by one
96-in.
(243,8-cm)
ring-follower
gate
and
one
96-in.
(243,8-cm)
hollow-jet valve
Capacity of
all outlets at
elevation 3,648 ft
(1.119
m):
cfs
(m3lsec)
15,000
(424')
Power
facilities
Location: At
the toe
of
Glen
Canyon
Dam
Total nameplate
capacity:
900,000
kw
Number
and
capacity
of
generators:
8 units
at 112,b00
kw each
Maximum head:
560
ft
(170
m)
Major
construction
quantities
Excavation, comnron,
for
dam
and
powerplant
Excavation, rock,
for
dam
and
powerplant
Excavation,
all
elasses, in
open
cut
for spillways
Excavation,
all
classes,
in
spillway
tunnels
Excavation,
all
classes,
in
diversion tunnels
Concrete
in
dam
Concrete in appurtenant
structures,
except
powerplant
Concrete
in
powerplant
Reinforcement
Tubing
and fittings
for
grouting
Spillway
radial
gates
and
hoist
Penstock and outlet
pipes
.Fixed-wheel
gates
and hoists
for
penstocks
Ring-follower
gates
and
hollow-
jet
valves
for
outlets
Trashrack metalwork
Structural
steel for
power-
plant
superstructure
All
other metalwork
required
for the
dam, outlets,
spillways,
and
power
features
Tubing
for cooling
conerete
ft
(m)
cu
yd
1,100,000
2,332,000
974,000
267,000
187,000
4,901,000
m3
841.000
1.783.000
745.000
204.000
143.000
3.747.000
250,000
191.000
220,000
168.000
lb
ks
37,100,000
16.828.000
GLEN CANYON DAM
328.000
787.000
.90.700
1.451.000
499.000
599.000
6,200,000
2.369.000
5,14o,ooo
2.331.000
outlets
were
checked
by
hydraulic
model
studies.
The
problems
of
temperature control
of
mass
con-
crete
in
the dam
and contraction
joint
gfouting
wene
also
extensively
sturdied.
The damsite is 12 miles
(19
km)
downstream
from
the
Arizona-fltah
stat;e
boundary.
When con-
struction
began,
the site was
one
of
the most iso-
lated
areas
of the
courtry.
This
desolate
region
imposed
major
problems
i:n
the
transportation
of
supplies
and
equiprment
from
established
areas
to
the damsite.
Bureau
engineers
initial,ly'
solved
the
problem
of
access by
construcl;ing
temporary roads,
pioneered
through the desert
to both s:ides
of
the river.
Con-
struction
of
temporary airsrbrips
on each side
of the
river
followed,
whir:h
provitled
ready
access
to the
damsite
and a me:rns
of
clr,ossing
the
canyon
for
engineers
and surveyors.
Subsequent
road
construc-
tion became
part
of'a first-rclass
highway
system
to
the
dam.
As
early
diversiron of the river
to
permit
work
on the riverbed
was
essentiial, the Bureau
awarded
the
first
major
contract irr October
1956
for
the
excavation
of a
4l-ft-diam,
(12,5-m),
/2-mileJong
(0,8-km)
diversibn
tunnel
thnough
the west
canyon
wall
at
the
damsite.
In
4.pril
L957,
the Merritt-
Chapman and
Scott Corporation
of New
York
CiW
was
awarded
the
prime
contract
for diversion
of the
river and
construction of tlne
east diversion
tunnel
of the same size
asi the
wesl;
diversion
tunnel,
and
construction
of the dam
powerplant
structure,
and
switchyard
area.
This
contract,
which
totaled
$107,955,522,
is
the
largest
single
construction
con-
tract ever awarded
by
the
Eureau
of
Reclamation.
To carry
forward
this
large
construction
under-
taking which
was
to
require more
than, ?
years
for
completion, the cont;ractor
nlarshdlled
an impressive
array of
ingenious
equipmernt; and facilities. Before
concrete could be
placed
in
the dam, more
than
3
years
were required
in
the' assembly and
erection
of construction facilities,
excavation,
construction
of cofferdams, and
diversioni of the river, in
addition
to
many
other related
preliminary
activities
pre-
ceding
construction
of
the
r:lam
proper.
Among
the
ma.jor construction faeilities were
two
5O-ton-capacity
(45-nnetric
ton) cableways
which
the contractor
installed
to
place
concrete
in
the dam and
to
lowe:r heavy
,equipment
to the canyon
floor.
Working together, the two eableways were
capable
of
handling
a
100-tora
(9l-metric
ton) Ioad.
The upper
cableway
spanned 2,050
ft
(625
m)
be-
tween
towers on op,posite
sid,es
of the
canyon.
The
main cable, largest ever built
for
this
purpose,
was
4 in.
(L0,2
cm)
in
diametrer,
weighed
38 lb/tt
(56,5
kglm)
per
foot,
and
had
a
strength
of
100
tons
(91
metric
tons).
Ther lower
cableway had a
span
of
1,800
ft
(54,9
m).
15
724,000
1,734,000
200,000
3,200,000
1,100,000
1,320,000
4,140,000
(1.262.000)