
7
4
ISOTHLKMAI
011
TKANSI’OKT
I95
20-25 years
for
pipes,
10
years
for
motors, pumps and five years
for
automation,
and control equipment.
In
reality, however, since the introduction of cathodic
protection, pipes have practically unlimited life. Even
so,
although the actual life
of
the equipment and fittings may be longer than the amortization periods mentioned
above, these periods may nevertheless be technologically justified, as the progress of
technology may make obsolete the equipment
in
use by putting on the market
equipment and fittings more advanced both technically and economically. The
relative depreciation (moral wear) of the existing installations
will
thus be
accelerated.
(B)
The
optimum trace
of
piplines
In case of an underground pipeline
of
pre-determined diameter, made of steel
of
a
given grade, the specific investment costs consist
of
two components. The first
of
these is the line cost
for
unit length, while the second component stands
for
the
specificcosts ofdigging the ditch, the laying
of
the pipeline, the backfilling, the clean-
up operations, and the damages to be paid to the owner of the ground, concerned.
Summarizing the different specific investment costs, from section to section
of
different lengths, along the selected trace, we obtain the total investment cost. The
main factors, influencing the optimum trace with the possibly smallest investment
cost, are the following: prohibited areas
for
pipeline laying (e.g. settlements, closed
military areas); the undulation
of
the area; the increase of the pipe-wall thickness at
the section passing through safety zones; the specific construction costs valid for
soils ofdifferent types; the cost
of
the intersection of natural,
or
man-made lakes
or
rivers, marshes; damages; the requirements concerning the branching lines; and
accessibility.
Before the designing
of the trace
of
the pipeline a design map must be prepared
that indicates all the parameters that may influence the construction costs
of
the
pipeline. Previously, the trace on this map was plotted by the designers on personal
considerations. Because
of
the high investment costs, the optimum version should
be determined by applying computers. Such procedures, discussed in the literature
may be classified as the network method, and as the method based on dynamic
programming(Lesic 1973; Babin
et
al.
1972; Shamir 1971). Both from the aspects
of
the data preparation, and the running time on the computer, the procedure based
upon dynamic programming proved to be the preferable one. In the next section the
essence
of
the design method developed at the Department of Petroleum
Engineering
of
the Miskolc Technical University for Heavy Industry, based on
Kaufmann’s procedure (1968) is discussed (Szilas
et
a/.
1978).
The process can be interpreted by the help
of
Fig.
7.4-8.
The head point
of
the
pipeline,
A,
and the tail end-point,
0,
are given. The dashed lines
xo.
.
.
x5
are the
border lines
of
areas
of
different specific construction costs.
For
the sake
of
lucidity,
the boundaries of the prohibited areas and level lines
of
the ground are not
indicated. The former will be referred to whileexplaining the next example, while the
impact
of
the latter is shown by the cost indicating at the connecting lines. On the