ably
dry,
the bond
test
was
performed
before
taking
up
bulk
enamelling
and
thus enamelled
patch
was
subjected
to
peel
test.
After
satisfactory results
the
coaltar
enamel
was applied
on
the
primed
surface
at
500'F
by
Hand
Daubing Brushes at
a thickness of
2.5
mm*0.8
mm
(3132
in.
*
ll32
in.).
As the dust
and
the
coaltar
fumes
are highly
poisonous
and have
deleterious
effect
on
human health, special
blowers of
capacity 311.5
cu m/min.
(11,000
cfm)
and static
pressure
of
37.5 cm
(15
in.) of
water
column
had
to
be
installed
to clear
the working
area. All
the
dust
and fumes
were
thus taken
out through
a
special
pipe
connected
near
the upstream end
of the
penstock
and
discharged
in the
atmosphere.
The
enamelled
surface
was
subjected to electrical
inspection
by
means of a
flaw
detector
bolt.
All
thinner
coatings
and
pin
holes
were
suitably covered with
enamel. The
life
of this
enamel
coating is
^about
30_
years.
Total painting
surface was
31,493
sq m
(3,39;000
sq
ft).
The.
entire
job
of
the
installation
(See
Figure
34)
a.nd
ppinting
wa_s
subjected
to
rigid
procedural-inspec-
tion b-y
an independent
agency
to
ensure
quitity
control
as
laid
down
in
the
relevant
specifications.
Cost
Data
Cost
of
steel
Cost
of
fabrication
Cost
of
haulage,
handling,
installation
at
site
and
welding,
etc.
Cost
of
painting
Rs. 124.8
lakhs
Rs.
25.0
lakhs
Rs.
41.0 lakhs
Rs.
32.2lakhs
Pu,rt fY-Initial
Storage,
Dfuintenar0ee
and
Operation
4.L Proposal
for
Early
Irrigation
In
view
of
the facts
that the
canal system
for
irrigation
was
already
ready
and there was
keen
demand
for
water
for
irrigation, it was
decided to
store
water
against
the
partially
completed
dam as
early as
possible.
The
early
irrigation
scheme envisaged
installation
of
temporary
regulation
gates
in
the
right
diversion tunnel. As
a first
step, the right
diversion
tunnel
was
closed by constructing a
coffer
dam
during
the
winter
season of 1957-58 and the river
was
diverted
through
the
left diversion
tunnel.
Outlets
were
provided
in a
temporary
plug
in
the right tunnel
and
regulating
gates
were
installed.
These
gates
were
worked
by
means of hoists
installed in
a
chamber
hallowed out
of solid sandstone
rock
above the tunnel
as
shown in Figure
35.
This
chamber
was
called
'hoist
chamber?
and
was
connected
to
the
dam
gallery
by
means of
an inclined tunnel
which
provided
access
to
the
hoist
chamber. The
left
diversion
tunnel
was
then closed
by dropping stop
logs
on 3
July
1958.
The water-level in
the
river upstream at that
time,
stood
a.t El. 345.46
m
(1199
ft) above
mean
sea lev-el.
During
this
period
a
regulated discharge of
255
cumecs
(9000
cusecs) or the
river
run-off,
whichever was less,
was
allowed to
pass
through
the
right
diversion tunnel
and
the
rest stoied.
Thus
was
started
the storage
of
water
for
the
first
time
in the
Bhakra
Reservoir,
called
Gobind Sagar.
Since spilling
over
the
partially
completed dam
during
1958
floods was
unavoidable,
two spillway
By
the
monsoon
of
1959,
the dam
had been
cons-
tructed up
to
El. 438.91
m
(1,440
ft)
in the
spillway
portion
whilst
some
abutment
blocks
had
been
raised to
El.
449.89 m
(1,476
ft)
above
mean
sea level.
Normal
water
releases
were
controlled
through
the
lower
tier
of
the
river
outlets
and
through the regulating works
of
the right
diversion
tunnel.
The
upper
tier
of
outlet
was
not
ready
yet.
4.2
f,'ailure of
Hoist
Chamber,
its
Repairs
and
Subsequent
Storage
In
August
1959,
when
the reservoir
stood
at
El.
436.17 m,
the water
flowing
through
the
right
diversion
tunnel damaged
the hoist
chamber.
The hoist
chamber
was
expected
to
provicle
adequate
control
until
the
reservoir
was
at
El.
449.8
m.
The
top
floor
above
the
gates
failed
when the reservoir was
at
El .
436 m.
The
gates
.were
bodily
lifted.
Nearly
255 cumecs
(9,000
cusecs) of water
escaped
through
the tunnel
-plug.
Water
entered
the dam
galleries
through
the
access
tunnel,
connecting the
hoist
chamber
with
the dam.
The
Left
Power
House,
where
turbines
and
generators
were being
installed, was
also
flooded.
This
was
the
63
-*1+J
"bj