28 NOVEMBER 2010 INTERNATIONAL WATER POWER & DAM CONSTRUCTION
REHABILITATION
Hudson River. The Mechanicville plant, still running on its original
40-cycle equipment, is considered the oldest continuously operating
hydro plant in the US.
Founded in 1924, Albany Engineering Corporation prides itself on
its innovative approach to hydropower projects while working within
the environmental context and historic integrity of each project. As
an example, the renewed plant at Stuyvesant Falls will incorporate
extensive environmental protection measures to safeguard resident
and migratory sh species. Albany Engineering will install an intake
system of its own design that offers extensive protection for sh, pre-
venting their entrainment and impingement.
This fish passage and protection system comprises a state-of-
the-art, positive exclusion inclined screen system constructed of a
water-ballasted-steel space frame that supports injection-moulded
polycarbonate screen panels. The system uses a high ratio of sweep-
ing velocity to through velocity that facilitates the passing of sh and
debris to the apex of the screen system where it is then passed down-
stream via a pipe conveyance.
The 1942 Spiers Falls turbine will not be used in the new plant due
to a penstock conguration that results in signicant head loss and
limited turbine output. Its accompanying generator is also undersized
for the turbine. They will be replaced by two identical vertical Francis
turbines, manufactured by Allis-Chalmers, with runner diameters of
1.12m with concrete spiral cases and elbow draft tubes. The turbines
will be directly connected to vertical generators manufactured by
Westinghouse Electric Company. These two turbines and generators,
originally installed at the Osage hydro plant at Lake of the Ozarks,
Missouri, are a perfect t.
The vertically congured units will permit installation of the gen-
erators above ood level, correcting a deciency existing in both the
original 1899 and 1942 congurations. The new units have a gener-
ating capacity of approximately 3000kW each, operating at 4160V,
60Hz alternating current at 1.0 power factor. The units, which oper-
ated until they were removed from Osage in 2009, are undergoing
complete refurbishment.
REFURBISHMENT
The new facility will use the existing 1899 dam and intake (rehabili-
tated in 1979). Leaks, erosion, corrosion and other factors of time
have affected the original penstocks. The two original steel penstocks
will be cleaned using high pressure water-jet blasting; some sections
will be replaced, and the interior throughout will be relined with a
modern polyurea coating system. After refurbishment, the penstocks
will make their transition to the turbines with their new hydrauli-
cally optimised terminal portions positioned safely beneath oor level
and encased in concrete. The deteriorated, original 1900 surge relief
towers will be replaced by synchronised bypass valves, hydraulically
connected to the turbine wicket gates, to assist in minimising pressure
surges during turbine operation.
Rehabilitation plans include installation of new unit breakers and
switchgear, station service, transformer, fused disconnect switches, and
lighting and surge arrestors. New turbine and generator controls and
protective devices will be installed in accordance with the requirements
of the local transmission provider, National Grid. New solid-state excit-
ers, lubrication and cooling systems, and hydraulic pressure units will
also be installed. New drive motors, hoist chain/cables, remote controls
and safety devices will update the powerhouse crane. A programmable
logic controller will operate the new equipment automatically with dig-
ital protective relaying and digital synchronisers.
The new plant equipment will use approximately 21.24m
3
/sec,
operating with a gross head of 30.48m and a net head of approxi-
mately 29.8m. The new generation facilities will be connected to the
National Grid transmission system through an adjacent 34,500V
switchyard. The newly expanded facility will generate approximately
20,000MWh annually.
The project is currently being relicensed under the Federal Energy
Regulatory Commission regulations. Plans to install minimum ow
turbines and generators at both the intake and powerhouse are
included in the relicensing. The combined capacity of these units
will be 900kW.
Because the plant is in the Stuyvesant Falls Historic District, the
powerhouse exterior will be restored carefully, including refurbish-
ment of windows and doors. The exquisitely detailed brickwork will
be re-pointed and repaired. Other updates include a potable water
supply, sanitary waste disposal facilities, lighting, security systems
and communications systems.
GREEN ENERGY
Construction work began in January 2010 and should be completed
by June 2011. Testing and commissioning will take place through the
fall of 2011. The planned rehabilitation of the hydroelectric station,
generating approximately 7.9MW, is scheduled for completion in
late 2011. And thus, Albany Engineering Corporation will bring this
century-old plant to life once again, supplying electricity to the region
as an historic beacon of renewable green energy.
The author is James A Besha, president,
Albany Engineering Corporation, 5 Washington Square,
Albany NY 12205, US.
Contact: Info@albanyengineering.com
IWP& DC
Above: Staff work together to remove an existing turbine in preparation for
the installation of the new turbines