11.5 Initial Planning 167
So, the document which accompanies the summoning of the meeting for the
Job Economical Review (EEC) shall contain all the elements described for
the Contract definition, the macroplanning of the activities, the scope of supply,
the risk and opportunity analysis, and finally the forecast profit-and-loss account
and cash flow curve. And also, with reference to the contract, it shall specify the
following: the effective date, the contractual payments and currency, the necessary
bank guarantees, the contractual deliveries with dates referred to the contractual
time schedule, the penalties for late delivery and performance, the requested per-
formance figures, the guarantee limits, miscellaneous such as laws, insurance,
standards; criticalities, such as e.g. the forecast difficulty in respecting the contrac-
tual time schedule owing to the technical departments’ overload, the high penalty
figures and their very unusual application conditions, or quite demanding perform-
ance tests.
On the basis of the provisional dates set at REO stage, we have then drawn up an
activity macroplanning document defining the main interchange dates to be shared
by the parties to the meeting and to be finally confirmed during detail verification,
but without deviating from the strategic objectives agreed during the meeting itself.
An exemplifying table is given later (Table 11.4).
The scope of supply shall be considered according to the contractual one plus
any clarifications and requests for clarifications to be discussed. Here follows a
practical example of the scope of supply to be written in the report:
1. Modification of roller table with aprons, cooling bed and lining-up rollers
2. Installation of cooling sprayers
3. Modification of roller table at cooling bed outlet and addition of two-layer
preparing systems: one north side towards the existing round bar finishing
station, and the other south side towards the new CLS and stacker
4. A CM with cutting-to-length beam north side
5. CLS with multi-strand straightener and mechanical shear south side
6. Roller table with trolleys at stacker inlet
7. Stacker with 24-m single magnetic heads
8. Steel strapping stations
9. Stack transfer and storage
10. Lubrication and hydraulic central units
11. Electric part and automation
Design data, such as requested productivity and maximum speed parameters,
starting materials and their characteristics, product mix and requirements.
The contents of the document to be discussed and updated at the KOM shall
report the specific clarification requests, if any, to be made to the technical, techno-
logical, purchasing and production departments.
Then all the delegates of the involved departments and business units are sum-
moned. In this phase, the information flow between the various departments is
defined and the first actual dates of which everybody shall take charge are set.
During these meetings and the subsequent ones, that will be single and specific,
what is important is to fix the correct lead times for the transfer of the information
between the different types of engineering and the different business units, with the