Explain.
Practical Considerations
While it is quite clear that the option to delay is embedded in many projects, there
are several problems associated with the use of option pricing models to value these
options. First, the underlying asset in this option, which is the project, is not traded,
making it difficult to estimate its value and variance. We would argue that the value can
be estimated from the expected cash flows and the discount rate for the project, albeit
with error. The variance is more difficult to estimate, however, since we are attempting
the estimate a variance in project value over time. One way of doing this is to run a series
of simulations capturing as many scenarios for the future as possible and then calculating
the variance in the present values derived from these simulations. An alternative is to use
the variances in stock prices of firms involved in the same business; thus, the stock price
variance of publicly traded biotechnology firms may be used as a proxy for the variance
of a biotechnology project’s cash flows.
Second, the behavior of prices over time may not conform to the price path
assumed by the option pricing models. In particular, the assumption that value follows a
diffusion process, and that the variance in value remains unchanged over time, may be
difficult to justify in the context of a project. For instance, a sudden technological change
may dramatically change the value of a project, either positively or negatively.
Third, there may be no specific period for which the firm has rights to the project.
Unlike the example above, in which the firm had exclusive rights to the project for 20
years, often the firm’s rights may be less clearly defined, both in terms of exclusivity and
time. For instance, a firm may have significant advantages over its competitors, which
may, in turn, provide it with the virtually exclusive rights to a project for a period of time.
The rights are not legal restrictions, however, and could erode faster than expected. In
such cases, the expected life of the project itself is uncertain and only an estimate.
6.9. ☞: Exclusive Rights and the Option Feature
A firm in an extremely competitive sector is faced with a project that has a negative net
present value currently and wants to know how much the option to delay the project is
worth. Which of the following would you think is the right response?