A Personal View of the Early Days of Mechatronics in Relation to Aerospace 237
procured by the customer. The task of managing the interfaces between the
equipments of different manufacturers was awarded by the customer to EASAMs,
the systems wing of Elliot Automation. As prime contractor, BAE was however
still ultimately responsible for delivering a fully operational weapons delivery
system, including equipments outside the remit of the EASAM contract.
Because of the lack of previous experience within the aerospace industry of a
project of this nature, much thought was given to ensuring that design
requirements of the total system were achieved prior to flight. The approach
chosen was to extend the individual development rigs to provide a total system.
A very important part of this total system is the pilot and as their operational
tolerances cannot be controlled to the same extent as other equipments, of
necessity, they must be included as a major part of the system! This also required
the cockpit to be spatially correct and the system to operate in real-time, primarily
with respect to response times. A simple ‘flight stimulation’, was all that was
required. Unlike a flight simulator, minor perturbations of an aerodynamic nature
were not necessary. The flight simulation programme also had to provide
stimulation to all the related equipment so that the loop was closed correctly in
real-time for multi-dimensional manoeuvres. In later stages of development, pilots
learned to fly the system on the rig as opposed to the aerodynamic handling which
still remained the province of the flight simulator. The resulting facility was later
used to train customer ground and aircrew, demonstrating the flexibility of the
design.
This early experience on the test facility enabled the same techniques to be
used in research work looking at the directions in which technology was moving.
For instance, in the mid-seventies, research into cathode ray technology and the
work on flat screens showed the future possibilities of active displays. The
technology at that stage was still very much for the next generation, but questions
had to be asked as to how it could eventually be utilised on aircraft.
In those early days, a key problem with using CRT displays was the extremes
of ambient lighting encountered during flight. To make reliable use of colour
requires the ability to maintain colour integrity under all lighting conditions from
total dark, to full sun above the clouds, a very severe regime. Not only did systems
have to be developed, but a means of achieving the development also had to be
thought through. In the case of colour displays, a lighting facility was required to
accurately recreate the conditions to be encountered in flight. A whole book could
be written on this topic alone! The facility created to develop the displays for the
Typhoon required a megawatt of lighting to achieve an accurate representation of
the light levels encountered above clouds and in bright sunlight. Imagine the
cooling required to protect the pilot from cooking!
This early work quickly highlighted the fact that for future projects to be
viable, delivery times to the customer had to be reduced. Exacerbating this
problem was the speed at which new technology was maturing. Even in the early
days, projects were being supplied to customers with out of date technology,
understandably not something customers were pleased with. This created a further
problem for the customer who felt they were being overcharged. The UK MOD