finally, the low-pressure turbines. At the exit of the low-pressure turbine, steam
pressure and temperature are extremely low – circa 0.05 bar and about 35º C.
At this point, the steam is condensed back to water. The condensed water is
then pumped back to the boiler and the cycle starts again. The turbines, high
pressure, and medium and low pressure are arranged in tandem, driving onto
the same shaft to which the alternator is connected.
Changes in electricity output are primarily controlled by alteration of the
water and fuel flows; but a change to these inputs will take time to work
through, because of the amount of heat stored in the boiler, furnace and duct-
work. Faster changes in turbine output are obtained by opening or closing the
throttle at the inlet to the high-pressure turbine.
It is vital to ensure that the oxygen content of the boiler water is very low
and the water extremely pure, otherwise the boilers and feed heaters will
corrode. Control of water quality is not too difficult during normal operation;
but during shutdown, air can leak into the steam system and, for various
reasons, contamination of the boiler water becomes more likely. These prob-
lems can lead to the cracking of major pieces of equipment during repeated
start-ups, because of a combination of bad water conditions and the thermally
induced stresses.
During normal operation, the furnace tubing, furnace structure, super-
heater, reheater and economizer run at high temperature. It will be apparent
that it will take a long time to bring these up to temperature, the heat coming
from the combustion of fuel. But there are many other pieces of equipment that
run hot, such as valves for control of steam flow, connecting pipelines and feed
heaters, all of which require steam to flow before these are at temperature. It
will take several hours to get a plant to produce power from a completely cold
start. Even if the plant has only been shut down overnight and is still quite
warm when the restart commences, it will still take about an hour before elec-
tricity can be can be generated, and perhaps another one to two hours before
the plant is up to full load. Shutdown is faster; but this too, must be controlled
or the stored heat in the plant will be wasted. Excess steam during these peri-
ods will be ‘dumped’ in the condenser.
During these periods of temperature change, some parts of major compo-
nents heat up faster than others, giving rise to differential expansion and high
stresses. This problem was recognized by the Central Electricity Generating
Board (CEGB), the original purchasers, who had the steam turbines of these
plants designed for 5000 hot starts, 1000 warm starts and 200 cold starts.
Nevertheless, premature failures can occur because of over-rapid start-ups and
shutdowns, or because of poor detailed design. It is also well understood that
as plant ages, the risks of these increase.
A low rate of start-up is a drawback of the steam plant of today; but more
advanced plant may take even longer to restart, despite modifications to elim-
inate some of the present shortcomings. But once in full operation, steam
plants are very efficient at controlling the grid frequency, voltage and load
changes. This is particularly true of the older type of steam plant, such designs
being of the ‘steam drum’ type, which has typified UK generating plant in the
past.
126 Renewable Electricity and the Grid
3189 J&J Renew Electricity Grid 6/8/07 7:35 PM Page 126