is generally consistent with the bedding dip and dip direction, and the
right abutment forms a stepped prole.
Using the geologic sections, it was possible to look for potential
interpolations of similar weak seams between boreholes in 2D (along
sections) and 3D (between sections). Potential planes of weakness
were identied between groups of boreholes and surface exposures.
A total of eight surfaces of potential weakness were identied at the
site, and these surfaces were named surface A-H. Their location rela-
tive to the dam is shown in Figure 5.
Stability analyses were undertaken along each of the surfaces iden-
tied. Surfaces A and C are located deep below the foundation and
were left in place. During construction it was found that surfaces D,
E, G, and H were identied at approximately the anticipated loca-
tions in the right abutment and spillway section. These surfaces were
treated in accordance with the plan developed during design. Surface
B was identied in the left abutment, and the foundation in this area
was initially blasted to the design level and the presence of Surface
B was conrmed. The geometry of Surface B was slightly different
from the geometry used in the design, so based on actual survey,
additional stability analyses were undertaken. Based on this analy-
sis it was determined that Surface B needed to be removed over the
majority of the footprint of the dam. An additional blast was done
to remove the rock above Surface B, gure 6 is a photo of the surface
after the additional rock removal.
The design also includes a grout curtain to seal potential seep-
age paths in the foundation. The double line grout curtain is being
installed using the GIN method, and grouting is generally being per-
formed from the approved RCC foundation level. In the abutment
sections the grout curtain is located in the footprint of the dam and
is being done in advance of RCC placement. In the primary spillway
section of the dam, grouting is being done from an overbuilt RCC
plinth upstream of the heel of the dam, allowing RCC placement to
proceed independently of grouting.
RIVER DIVER SION AND DEWATERING
Flows in the Teviot Brook are similar to those in many Australian
rivers and streams, where there are periods of low ows, punc-
tuated by high ow events. Taking this ood risk into account,
the nal diversion arrangement consisted of a 6m high cofferdam
which was designed, with reno mattresses, to be overtopped and
had a sheetpile cuttoff down to foundation rock through the more
permeable alluvial materials in the main river channel.
The river has been diverted into a buried steel conduit for the duration
of construction. The diversion pipe consists of a 2.4m diameter steel
pipe, which is concrete encased under the foot print of the dam. The
capacity of the diversion is approximately 25m
3
/sec. In the event the cof-
ferdam is overtopped during the rst year of construction, various design
measures have been adopted to control the ow into the dam excavation
area, minimising the clean up and ensuring rapid dewatering.
In addition, a series of dewatering wells are provided to dewater
the alluvial material and rock in the foundation area, so as to mini-
mise the ground water inow into the 15m deep excavation.
DAM SECTION AND DESIGN
Analyses performed for the dam included static and dynamic stabil-
ity analyses. Stability analyses were performed along RCC lift joints
within the dam, along the RCC/Rock interface, along typical bedding
planes in the foundation, and along specic defects identied in the
foundation. A nite element model was developed to estimate stress-
es in the dam during an earthquake, and seismic deformation analyses
were performed to estimate displacements during an earthquake.
The dam section was governed by stability analysis along bedding
planes and specic defects in the foundation. Shear strength prop-
erties for the RCC/Rock interface were developed using the Barton
criteria for rough surfaces. Shear strength properties for bedding
planes were developed using a combination of the Barton criteria
and measured roughness values. Shear strength properties for weak
layers in the foundation were developed using direct shear testing. A
section with a crest width of six meters and a downstream slope of
0.8H:1.0V was selected based on the analysis. A typical section for
the primary spillway shown in Figure 7.
Design features at the dam include a 400mm thick layer of conven-
tional concrete facing, a drainage gallery, crest to gallery drains, foun-
dation drains, and reinforced concrete crest sections. Typical monolith
joints in the RCC are located at 30m spacing, with intermediate joints
in the facing concrete at 7.5m spacing. The thermal analysis indicates
the monolith joint spacing can be adjusted, so the actual location of
monolith joints are being adjusted to suit foundation conditions.
SPILLWAY
The spillway at Wyaralong dam is required to pass the probable
maximum ood, which has a design inow of around 7680m
3
/sec.
Various spillway options were investigated during the value-man-
agement phase of the project, including combinations of primary,
secondary and tertiary spillways located both within the dam section
and remote from the main wall.
The adopted arrangement comprises a centrally located, un-gated
primary spillway with a smooth downstream face. A 25m wide still-
ing basin is located at the base of the primary spillway. The design
also incorporates a stepped faced secondary spillway on the left abut-
ment of the main wall, which is designed to operate at oods less
frequent than the 1 in 100 AEP event. Flows over the secondary
spillway are directed along the toe of the secondary spillway in a
concrete-lined apron channel to the main stilling basin. For ood
events greater than the 1 in 2000 AEP event, the capacity of the sec-
ondary spillway apron channel is exceeded and ows spill out across
the left abutment towards the river channel.
Extensive investigations were undertaken during the design phase
to assess the behaviour of the spillways, with particular attention
to the erosion potential of the left abutment for ood events which
exceed the secondary spillway apron channel capacity. Two physical
model studies were conducted, comprising:
r 1 in 80 scale model of the dam
r 1 in 30 scale model of the primary spillway, used to assess the
performance of the shway, outlet works and stilling basin under
low ow events.
WWW.WATERPOWERMAGAZINE.COM AUGUST 2010 17
AUSTRALASIA
Above: Figure 3 – Foundation preparation on left abutment;
Right: Figure 4 – Foundation preparation on right abutment