51
b). Thickened Tailings Disposal (TTD) System. The aim of the TTD system is to
eliminate the possibility of dam failures and prevent the pollution attributed to
conventional impoundments. It also aims to reduce the cost of reclaiming conventional
impoundments after closure. These aims are achieved by depositing thickened tailings
from a topographical high, or from central ramps or towers, so as to form a self
supporting mound or ridge of the stored tailings. This minimises the requirement for
confining dams, eliminates the need for a settling pond, and shapes the discharged
tailings into a self-draining, easily reclaimable shape, having slopes of 2 to 6 percent.
The removal of much of the process water from the tailings is achieved by passing
the tailings through high compression thickeners.
2
/
3
to
4
/
5
of the process water is
decanted from the thickeners as clear overflow and is recycled back into the process.
The thickened tailings do not segregate, so that all the particle sizes stay together
forming a homogeneous material with a high capillary suction: when placed layer by
layer, it dries to near its shrinkage limit and becomes dilative under earthquake
strains, thus preventing liquefaction. It tends to remain saturated almost to the surface,
thus preventing the development of acid drainage and so becomes suitable for
eventual topsoil and vegetation. Detailed description of the system has been given by
Robinsky (1999).
Example. The Falconbridge Ltd 12,000 ton/day copper/zinc Kidd Creek mine in
Ontario, Canada, was converted in 1972 to use the TTD system to avoid having to
build traditional tailings dams on very soft and sensitive clay foundations. The disposal
area of 1420 ha, with an average diameter of 1.5 km is on a topographical high
surrounded on three sides by a river. Initially discharge was from a series of spigots
from a central ramp, but later a single point discharge was placed at the north end of
the area with the intention of moving it progressively to the south to create a ridge so
as to allow of progressive reclamation from the north end while deposition continues.
The slopes formed are between 2.5 and 3 percent and the only retaining dam required
is 10 m high across a small valley. This Kidd Creek operation was the first TTD project
and while considered experimental at first, the system has progressively evolved to
form a successful method of tailings deposition, now operating in its 24
th
year.
Example. The open pit nickel sulphide mine at the Mount Keith operation in
Western Australia produces 11.5 x 10
6
tonnes of tailings a year. The area is relatively
flat and semi-arid, with an average annual pan evaporation of 3800 mm, while the
rainfall is only 220 mm. As a cheaper and potentially safer method of tailings storage
than the traditional paddock method, mine management chose the thickened tailings
disposal system, originally proposed by Professor Robinsky in 1968. Following an
intensive field and laboratory investigation, they designed the storage facility to be
able to accommodate 250 x 10
6
tonnes of tailings at a rate of up to 15 x 10
6
tonnes/year. The storage area is 1700 ha, with an average diameter of 4.6 km on
land with a very slight fall of only 12 to 14 m from west to east. A perimeter bund
14 km long surrounds the site to prevent the spread of any materials that might be
carried by rainfall run-off. There is a central riser pipe surrounded by 8 other risers
35 to 45 m high and a fully automated three-train, two stage pumping station able to
deliver the thickened tailings to any riser at a rate of 3 x 10
3
m
3
per hour.
Underdrainage was installed in the ground surrounding each riser, plus open drainage
to collect decanted water. There are back-up systems including spare risers, bypass
line, dump valves etc., and the facility is monitored remotely continuously by telemetry.
A computer programme gives comparison between predicted and actual mound