Guide on How to Develop a Small Hydropower plant ESHA 2004
vegetation through excavation work, turbidity of the water and downstream sediment deposition,
etc. To mitigate such impacts it is strongly recommended that the excavation work should be
undertaken in the low water season and the disturbed ground restored as soon as possible. In any
case these impacts are always transitory and do not constitute a serious obstacle to the
administrative authorisation procedure.
In view of its protective role against riverine erosion it is wise to restore and reinforce the riverbank
vegetation that may have been damaged during construction of the hydraulic structures. It should
be noted that the ground should be repopulated with indigenous species, best adapted to the local
conditions.
The impact assessment study should take account of the effects of dispersing excavated material in
the stream and the unfavourable consequences of construction workers living in a usually
uninhabited area during the construction period. This impact, which may be negative if the scheme
is located in a natural park, would be positive in a non-sensitive area by increasing the level of its
activity. Vehicle emissions, excavation dust, the high noise level and other minor burdens
contribute to damaging the environment when the scheme is located in sensitive areas. To mitigate
the above impacts the traffic operation must be carefully planned to eliminate unnecessary
movements and to keep all traffic to a minimum.
On the positive side, it should be noted that the increase in the level of activity in an area, by using
local manpower and small local subcontractors during the construction phase is to be welcomed.
7.4 Impacts arising from the operation of the scheme
7.4.1 Sonic impacts
The allowable level of noise depends on the local population or isolated houses near to the
powerhouse. The noise comes mainly from the turbines and, when used, from the speed increasers.
Nowadays noise inside the powerhouse can be reduced, if necessary, to levels in the order of 70
dBA, almost imperceptible when outside.
Concerning sonic impact, the Fiskeby
3
power plant in Norrköping, Sweden is an example to be
followed. The scheme owner wanted a maximum internal sound level of 80 dBA inside the
powerhouse at full operation. The maximum allowed external sound level, at night, was set at 40
dBA in the surroundings of some houses located about 100 metres away.
To reach these levels of noise it was decided that all the components - turbines, speed increasers,
and asynchronous generators - were bought in one package from one well-known supplier. The
purchase contract specified the level of noise to be attained in full operation leaving the necessary
measures to fulfil the demands to the manufacturer. The supplier adopted the following measures:
very small tolerances in the gear manufacturing; sound insulating blankets over the turbine casing;
water cooling instead of air cooling of the generator and a careful design of ancillary components.
As well as the usual thermal insulation, the building was provided with acoustic insulation.
Consequently, the attained level of noise varied between 66 dBA and 74 dBA, some 20 dBA lower
than the average Swedish powerhouses. Having a single supplier, the issue of responsibility was
eliminated.
The external noise level reduction was obtained by using vibration insulation of the powerhouse
walls and roof. The principle for the vibration reduction system was to let the base slab, concrete
waterways and pillars for the overhead crane be excited by vibration from the turbine units. The
205