178
8: Variance analysis ⏐ Part B Standard costing
4.1 Example: variable overhead variances
Suppose that the variable production overhead cost of product X is as follows.
2 hours at $1.50 = $3 per unit
During period 6, 400 units of product X were made. The labour force worked 820 hours, of which 60 hours were
recorded as idle time. The variable overhead cost was $1,230.
Calculate the following variances.
(a) The variable production overhead total variance
(b) The variable production overhead expenditure variance
(c) The variable production overhead efficiency variance
Since this example relates to variable production costs, the total variance is based on actual units of production. (If the
overhead had been a variable selling cost, the variance would be based on sales volumes.)
$
400 units of product X should cost (
×
$3)
1,200
but did cost
1,230
Variable production overhead total variance
30
(A)
4.2 Subdividing the variable overhead total variance
In many variance reporting systems, the variance analysis goes no further, and expenditure and efficiency variances are
not calculated. However, the adverse variance of $30 may be explained as the sum of two factors.
(a) The hourly rate of spending on variable production overheads was higher than it should have been, that is
there is an
expenditure variance
.
(b) The labour force worked inefficiently, and took longer to make the output than it should have done. This
means that spending on variable production overhead was higher than it should have been, in other words
there is an
efficiency (productivity) variance
. The variable production overhead efficiency variance is
exactly the same, in hours, as the direct labour efficiency variance, and occurs for the same reasons.
It is usually assumed that
variable overheads are incurred during active working hours
, but are not incurred during idle
time (for example the machines are not running, therefore power is not being consumed, and no direct materials are being
used). This means in our example that although the labour force was paid for 820 hours, they were actively working for only
760 of those hours and so variable production overhead spending occurred during 760 hours.
4.2.1 The variable overhead expenditure variance
This is the difference between the amount of variable overhead that should have been incurred in the actual hours actively
worked, and the actual amount of variable overhead incurred. Refer to the data in Section 4.1.
$
760 hours of variable production overhead should cost (
×
$1.50)
1,140
but did cost
1,230
Variable production overhead expenditure variance
90
(A)
4.2.2 The variable overhead efficiency variance
If you already know the direct labour efficiency variance, the variable overhead efficiency variance is exactly the same in
hours, but priced at the variable production overhead rate per hour. In the example in Section 4.1, the efficiency variance
would be as follows.
199433 www.ebooks2000.blogspot.com