i. AS MOST HIMALAYAN RIVERS, LIKE SATLUJ CARRYING HEAVY SILT
LOAD, THIS PROBLEM HAS TO BE ADDRESSED MOST EFFECTIVELY IN
DESIGN STAGE OF ALL FUTURE PROJECTS
ii. HVOF COATING OF UNDER WATER PARTS HAVE GIVEN GOOD RESULTS
AT NJHEP AND COULD BE TRIED ON OTHER PROJECTS WITH SIMILAR
PROBLEMS
iii. AN UPPER LIMIT OF 2000 PPM PASSING THROUGH DRAFT TUBES AND A
TOTAL QUANTUM OF 7 LAC TONNES OF SILT LOAD, APPEARS TO BE
REASONABLE IN CASE OF NJHEP, AT THIS STAGE.
iv. FOR MAXIMISING GENERATION AND MINIMISING SILT DAMAGE IN ANY
RIVER BASIN, A JUDICIOUS COMBINATION OF STORAGE AND RUN-OFF
THE RIVER PROJECT IS ESSENTIAL. MOTHER STORAGE AT KHAB IS
IDEAL FOR SUCCESS OF ALL D/S PROJECTS.
v. THE SHORT AND LONG TERMS MEASURES OUTLINED IN THE PAPER,
WHEN FULLY IMPLEMENTED, WILL GREATLY ENHANCE POWER
GENERATION AND MINIMISE DAMAGE IN ALL PROJECTS D/S OF KHAB
CONCLUSION