Code of Standard Practice for Steel Buildings and Bridges, March 18, 2005
AMERICAN INSTITUTE OF STEEL CONSTRUCTION
16.3-43
The substitution of other working points is permitted for ease of reference,
provided they are based upon the above definitions.
The tolerances on Structural Steel erection shall be in accordance with
the requirements in Sections 7.13.1 through 7.13.3.
Commentary:
The erection tolerances defined in this Section have been developed through
long-standing usage as practical criteria for the erection of Structural Steel.
Erection tolerances were first defined in the 1924 edition of this Code in Section
7(f), “Plumbing Up.” With the changes that took place in the types and use of
materials in building construction after World War II, and the increasing
demand by Architects and Owners for more specific tolerances, AISC adopted
new standards for erection tolerances in Section 7(h) of the March 15, 1959
edition of this Code. Experience has proven that those tolerances can be
economically obtained.
Differential column shortening may be a consideration in design and
construction. In some cases, it may occur due to variability in the accumulation
of dead load among different columns (see Figure C–7.1). In other cases, it may
be characteristic of the structural system that is employed in the design.
Consideration of the effects of differential column shortening may be very
important, such as when the slab thickness is reduced, when electrical and other
similar fittings mounted on the Structural Steel are intended to be flush with the
finished floor and when there is little clearance between bottoms of beams and
the tops of door frames or ductwork.
Expansion and contraction in a Structural Steel frame may also be a
consideration in the design and construction. Steel will expand or contract
approximately 1/8 in. per 100 ft for each change of 15°F [2 mm per 10 000 mm
for each change of 15°C] in temperature. This change in length can be assumed
to act about the center of rigidity. When anchored to their foundations, end
columns will be plumb only when the steel is at normal temperature (see Figure
C–7.2). It is therefore necessary to correct field measurements of offsets to the
structure from established baselines for the expansion or contraction of the
exposed Structural Steel frame. For example, a 200-ft-long [60 000-m-long]
building that is plumbed up at 100°F [38°C] should have working points at the
tops of the end columns positioned 1/2 in. [14 mm] further apart than the
working points at the corresponding bases in order for the columns to be plumb
at 70°F [21°C]. Differential temperature effects on column length should also be
taken into account in plumbing surveys when tall Structural Steel frames are
subjected to sun exposure on one side.
The alignment of lintels, spandrels, wall supports and similar members
that are used to connect other building construction units to the Structural Steel
frame should have an adjustment of sufficient magnitude to allow for the
accumulation of mill tolerances and fabrication tolerances, as well as the
erection tolerances. See Figure C–7.3.