The base budget is subdivided into two parts: the main one is the baseline,
whereas a smaller amount is set aside for contingencies (management reserve).
Management reserve is particularly important in the case of work orders, when the
contract includes penalty clauses for late deliveries; considering the inevitable
randomness of some variables, a certain budget percentage is necessary to reduce
the risk of project delays.
The baseline on the other hand is the available sum that can be used to carry out
the activities relative to the project. It is so called because its evolution in time can
be depicted as a line. It usually has an S shape, since during the first stages expendi-
ture is low, and then rises sharply, to finally decrease in the last stages of the project
(Figs. 10.6 and 10.7). Therefore, in a cost/time Cartesian representation, the base-
line curve starts at the origin of the axis to reach a final point, which indicates both
the duration of the project and its overall cost (commonly known as budget), which
corresponds to the maximum value of the baseline.
This sum includes the so-called Cost Accounts (CA) that are relative to the Work
Packages (WP) carried out by well-established resources. The integration between
costs and work schedule is termed as “Cost/Schedule Control System Criteria – C/S
CSC” (or also “C.Spec.”) by the Department of Defense – DoD – or “533 System”
by the National Aeronautics and Space Administration – NASA.
In other words, the CA are defined by combining the POBS with the WBS (who
does what, respectively): the tasks described in the WBS are aggregated into work
packages; organizational managers are responsible for these WP, and they have a
certain CA at their disposal to pay for the necessary resources. Figure 10.5 could
also include a third dimension, rising up from the page, which structures the
elementary units of the CA, to rebuild the PPBS.
Therefore, the project manager delegates technical and managerial responsibility for
the various chunks of the WBS (i.e. the activities) to WP manager, who is also respon-
sible for the CA. The project manager retains a part of the baseline for the direct, overall
management of the project: this portion is known as undistributed budget (Fig. 10.4).
The criteria used to define each CA must be based on the efforts needed to
deliver the activities of the project; these efforts can be classified as follows:
– Measured Effort (ME) – an effort that can be divided into work packages (WP)
Consisting of activities (30-40 at the most) of limited duration, and whose out-
puts (deliverables) can be measured directly
– Apportioned Effort (AE) – an effort that by itself is not readily divisible into
short-span work packages but that is directly proportional to the ME, and there-
fore to the WP (these are indirect activities, but the effort they require is linked
to the amount of direct work expressed by the WP)
– Level of Effort (LE) – an effort of a general or supportive nature, which is not
proportional to the ME and cannot be ascribed to the WP (fixed activities, inde-
pendent of the size of the WP)
Hence, in order to carry out the operations described in the WP, it is necessary
to have a CA that takes into account the ME, AE and LE; work packages deliver
partial outputs known as deliverables, that document/concretise the work carried
10.3 Cost Budgeting: Budget Breakdown Structure, Baseline, Cost Accounts 127