Guide on How to Develop a Small Hydropower Plant ESHA 2004
The application file is to be sent to the préfet who forwards it to the service in charge of the police
of water (SPE, “service chargé de la police des Eaux”). The SPE studies the file and transmits it to
the regional public authorities: Direction régionale de l’industrie, de la recherche et de
l’environnement (DRIRE), Direction régionale de l’environnement (DIREN), Conseil supérieur de
la pêche (CSP). It can ask the developer for more information. After reception of the various
opinions, the SPE forwards the file to the préfet. If the préfet agrees with the project, he passes a
decree deciding a public inquiry.
After receiving the advice of the County Council, the Mayors and of all the concerned services, a
water right is written and proposed by the SPE. The préfet takes his final decision. If he agrees, he
signs an authorization decree and the works are executed. At the end of the works, the equipment is
checked and the agreement of the public authority is given in a report of checking.
9.3.2.3 Connection to the grid
According to the law of the 10 February 2000 and its decrees, the grid has the obligation to buy the
electricity generated by RES plants of capacity less than 12 MW, but the producer has to
demonstrate that he cannot sell its production at a good price to another client and he must forward
an application to the utility. For capacities less than 10 MW, the connection is done to the
distribution grid (low voltage). For capacities upper than 10 MW, the plant is connected to the high
voltage electricity transfer grid.
In parallel, the developer has two procedures to follow:
• An application of authorization to run the plant is to be sent to the ministry in charge of
energy (2000-877 decree of 7 September 2000).
• A certificate of purchasing obligation is to be asked to the regional Direction of Industry.
9.3.3 Ireland
In Ireland, the procedures are as follows:
9.3.3.1 Planning Permission
The planning application consists of an application form and of several documents maps and plans.
The planner must take all references to renewable energy in the Development Plan into account.
Development Plans must be reviewed every 5 years.
The developer has to provide information on how the development will impact on the area. This is
done via an Environmental Impact Statement (EIS). An EIS will also be required if the development
is located in a National Heritage Area (NHA), Special Area of Conservation (SAC), Special
Protection Area (SPA) or other designated areas.
An Environmental Impact Statement is legally defined in the Local Government (Planning and
Development) Regulations, 1990. A typical EIS would contain examinations of the impact of the
project on the following: Water, soils & geology, air quality, noise, flora & fauna, cultural heritage,
electromagnetic fields, visual impact, climatic effects, interaction of impacts, alternatives. An EIS
will decide whether the application is successful or not. It needs to be clear, thorough and cover all
areas of interest to the planner. Planners, and officers from the statutory bodies, are available to
provide advice on scooping an EIS.
267