
//INTEGRAS/KCG/P AGIN ATION/ WILEY /WPS /FINALS_1 4-12- 04/0470855088_ 23_CHA22 .3D – 484 – [479–504/26]
17.12.2004 10:46PM
turbines are connected to one feeder. The maximum number of turbines on each feeder
is determined by the maximum rating of the cable (Brakelmann, 2003). If the cable is
damaged the whole feeder will be disconnected until the fault is repaired. Redundancy
might be achieved by enabling connections be tween feeders. The last wind turbine in one
feeder could be connected to the last turbine in the next feeder, for instance. During
normal operation, this connection would be open. If there is a fault in one of these two
feeders, the connection would be closed.
For this, additional equipment would be required to isolate the fault. The goal is that
as many wind turbines as possible remain connected to the grid. It has also to be taken
into account that the number of wind turbines that may be connected to one feeder will
be lower, as the maximum cable rating must be able to cop e with twice as many turbines
in case the fault is close to the first turbine within one feeder. Today, the likelihood of a
fault and the associated costs are assumed to be lower than the costs for the additional
equipment – therefore, redundancy is not taken into consideration. In order to reduce
the likelihood of damage, the cables are usually buried 1–2 m into the seabed to protect
them from ships’ anchors and strong sea currents.
Usually, the cable from the offshore wind farm to the shore does not include any
redundancy either (see also Figure 22.1, Alternative A). A fault on this cable, however,
will result in a loss that is equivalent to the entire wind farm. The economic consequences
from such a fault may be huge. The repair might take months, depending on the
availability and current position of cable repair ships. It is, however, very difficult to
protect the cable from damage, particularly if the cable crosses major shipping routes. At
the First International Workshop on Transmission Networks for Offshore Wind Farms in
Stockholm, Sweden, it was reported that the anchors of large ships could dig down up to
13 m into the seabed. It is not practically viable to bury a cable at such a depth.
Redundancy could be achieved by using another, backup, cable following another route
to shore (see Figure 22.1, Alternative B). Besides the significant costs of such a second
connection to shore, it might be also very difficult to carry this out in practice. At many
locations, environmental restrictions would make it very difficult to find a second cabling
route. A second connection point to the onshore network might not always be available
either. Currently, no developers of offshore wind farms seriously consider any redundancy
for the onshore cabling. Experience from the operation of the first large offshore wind farms
will show whether redundancy for onshore connections will become necessary in future.
22.3 Transmission System to Shore
For the cabling to shore, either high-voltage alternating-current (HVAC) or high-
voltage direct-current (HVDC) connections could be used. For HVDC connections,
there are two technical options: line commutated converter (LCC) based HVDC and
voltage source co nverter (VSC) based HVDC technology.
All offshore wind farms that are currently operating (as of December 2003) have
adopted an AC alternative, and all those planned to be inst alled within the near future
(1–2 years) will also use an AC solution. This is because of the comparative ly small size
and/or the short distance between the shore and the existing wind farms. As the size of
future wind farms and the distance to shore is likely to increase, this might change.
484 Transmission Systems for Offshore Wind Farms